Orange County NC Website
EXHIBIT-2 <br />ORANGE COUNTY TRANSFER STATION <br />TENTATIVE IMPLEMENTATION SCHEDULE <br />ACTIVITY <br />DURATION <br />START DATE <br />COMPLETION <br />DATE <br />BOCC Site Selection <br />12/11/08 <br />Property Acquisition <br />2 Months <br />12/11/2008 <br />2/9/2009 <br />Concept Design <br />2 Months <br />12/11/2008 <br />2/9/2009 <br />Site Plan Design <br />2 Months <br />2/9/2009 <br />4/10/2008 <br />OC Site Plan Review & Approval <br />3 Months <br />4/10/2009 <br />7/9/2009 <br />Permitting <br />5 Months <br />2/9/2009 <br />7/9/2009 <br />Facility Design <br />7 Months <br />2/9/2009 <br />9/7/2009 <br />Development of Final Construction <br />Documents <br />• Site Preparation Package <br />1 -1/2 Months <br />7/9/2009 <br />8/24/2009 <br />• General Building Contract <br />3 Months <br />9/7/2009 <br />12/10/2009 <br />Advertisement, Bidding & <br />Contract Award <br />• Site Preparation Package <br />2 -1/2 Months <br />8/24/2009 <br />11/6/2009 <br />• General Building Contract <br />3 Months <br />12/10/2009 <br />3/8/2010 <br />Project Construction <br />• Site Preparation Package <br />4 Months <br />11/6/2009 <br />3/8/2010 <br />• General Building Contract <br />14 -1/2 Months <br />3/8/2010 <br />5/20/2011 <br />November 10, 2008 Page 1 <br />