2 <br />Facility site predicts a better than average probability of finding rock during the sewer <br />construction process, thereby prompting the need to reserve contingency funds ($36,242) for <br />that eventuality. Additional approvals by the Board would be sought should the rock <br />contingency cause the project to exceed the $284,000 set aside. <br />RECOMMENDATION(S): The Manager recommends the Board approve the change order to <br />Clancy and Theys in the amount of $247,758 for the sewer construction associated with the <br />Animal Services Facility and the leachate pond at the Landfill; and to further authorize the <br />Manager to approve change orders up to an additional $36,242, which represents the difference <br />between the budgeted amount ($284,000) and the construction amount ($247,758). <br />