Smith Middle School Construction/K-12 Campus
<br /> Chapel Hill-Carrboro City Schools 3
<br /> Capital Project Ordinance
<br /> Be it ordained by the Orange County Board of County Commissioners that pursuant to
<br /> Section 13.2 of Chapter 159 of the General Statutes of North Carolina, the following capital
<br /> project is hereby adopted.
<br /> Section 1. The project authorized provides funds to construct Smith Middle School, co-
<br /> located on the Seawell Elementary School and' Chapel Hill High School
<br /> campus. This project will be financed with proceeds from the 1997 Park and
<br /> Recreation Bonds, 1997 School Bonds, and School Construction Impact Fees.
<br /> Section 2. The officers of the County are hereby directed to proceed with the project within
<br /> the budget contained herein.
<br /> Section 3. The following revenue is anticipated to complete this project:
<br /> nrougn FY Appropriatie-T—i-fi-ra—ug-fF.
<br /> 2001.02 FY 2002-03 2002-03
<br /> School ons ruc ion
<br /> Im act Fees $1 ,800,000 $0 $1,800,000
<br /> 7-997 ar ecrea ion
<br /> Bond Funds $0 $114,058 $114,058
<br /> School on
<br /> Funds $18,000,000 $0 $18,000,000
<br /> Total Funding $19,$00,000 114,058 19,914,058
<br /> Section 4. The following amount is appropriated for this project:
<br /> nrougn FY Appropriated roug
<br /> 2001-02 FY 2002-03 2002-03
<br /> Site Ac uisition $22,600 0 22,600
<br /> Site Develo ment $2,744,000 0 $2,744,000
<br /> Fees $1,603,000 $0 $1,603,000
<br /> Construction $13,159,924 $0 $13,159,924
<br /> Technology $831,000 0 $831,000
<br /> Moveable Equipment $685,000 $0 $685.000
<br /> Start-U Costs 350,000 0 350,000
<br /> Multi- Fields 0 $114,058 $114,058
<br /> [Contingency $404,476 0 404,476
<br /> Total Costs $19,800,000 1 $114,05a $19,914,058
<br /> Section 5. The following amount is transferred from this project:
<br /> nrougn FY Appropriated roug
<br /> 2001.02 FY 2002-03 2002-03
<br /> rans er o emen ary
<br /> School #9 $380,000 $0 $380,000
<br /> Section 6. The following amount remains appropriated for this project:
<br /> Remaining
<br /> Sman middle School Pro'ect Bud et Less: Transfer Budget
<br /> Construction $19,914,058 $380,000) $19,534,058