<br /> additional funding. While the intention had been to provide the Board with a series of additional
<br /> construction options, including more daylighting and solar installation, due to the tremendous cost
<br /> savings achieved through the bidding process, these elements have already been incorporated
<br /> into the GMP.
<br /> Crisis Diversion Facility- Final Project Budget-June 6th
<br /> GMP (Construction and Indirect Costs) $22,906,906
<br /> Land $1,353,266
<br /> Design/Other Services $2,142,227
<br /> Furniture $525,983
<br /> Environmental Impact and Related Fees $132,785
<br /> Special Inspections $75,000
<br /> Commissioning $100,868
<br /> Owner's Contingency $1,850,000
<br /> Offsite lighting $100,000
<br /> AN $25,000
<br /> Low Voltage $75,000
<br /> Security $125,000
<br /> Total: $29,412,035
<br /> The current project schedule, as shown below, projects construction starting in August and
<br /> occupancy expected in the spring of 2028.
<br /> Project Schedule
<br /> Schedule for the Construction of the Crisis
<br /> Diversion Facility
<br /> Board Approval of GMP June 2026
<br /> Start of Construction August 2026
<br /> Construction Completed Winter 2028
<br /> Occupancy Spring 2028
<br /> FINANCIAL IMPACT: Budget Amendment #12-A allocates $3,358,685 in additional funding to
<br /> cover the increased cost for the construction of the facility over the original project funded in the
<br /> FY 2025-35 Capital Investment Plan. Staff also worked with Alliance and confirmed that
<br /> $1,100,000 of the Cardinal Reserve could be dedicated towards the Crisis Diversion Facility.
<br /> These two (2) changes are reflected in the amended project ordinance:
<br /> Crisis Diversion Facility($3,358,685) - Project# 10080
<br /> Revenues for this project:
<br /> Current FY 2025-26 FY 2025-26
<br /> FY 2025-26 Amendment Revised
<br /> Cardinal Reserve $1,823,121 ($723,121) $1,100,000
<br /> From General Fund $250,000 $0 $250,000
<br /> Alternative Financing $23,980,229 $4,081,806 $28,062,035
<br /> Total Project Funding $26,053,350 $3,358,685 $29,412,035