Orange County Emergency Services -Generator
<br />PDC Project 24030 Execution and Closeout Requirements 01 70 00 - 4
<br />H.Fit work air tight to pipes,sleeves,ducts,conduit,and other penetrations through surfaces.
<br />I.At penetrations of fire rated walls,partitions,ceiling,or floor construction,completely seal voids
<br />with fire rated material in accordance with Section 07 84 00,to full thickness of the penetrated
<br />element.
<br />J.Patching:
<br />1.Finish patched surfaces to match finish that existed prior to patching. On continuous
<br />surfaces,refinish to nearest intersection or natural break. For an assembly,refinish entire
<br />unit.
<br />2.Match color,texture,and appearance.
<br />3.Repair patched surfaces that are damaged,lifted,discolored,or showing other imperfections
<br />due to patching work.If defects are due to condition of substrate,repair substrate prior to
<br />repairing finish.
<br />3.06 PROGRESS CLEANING
<br />A.Maintain areas free of waste materials,debris,and rubbish. Maintain site in a clean and orderly
<br />condition.
<br />B.Remove debris and rubbish from pipe chases,plenums,attics,crawl spaces,and other closed or
<br />remote spaces,prior to enclosing the space.
<br />C.Broom and vacuum clean interior areas prior to start of surface finishing,and continue cleaning to
<br />eliminate dust.
<br />D.Collect and remove waste materials,debris,and trash/rubbish from site periodically and dispose
<br />off-site;do not burn or bury.
<br />3.07 PROTECTION OF INSTALLED WORK
<br />A.Protect installed work from damage by construction operations.
<br />B.Provide special protection where specified in individual specification sections.
<br />C.Provide temporary and removable protection for installed products.Control activity in immediate
<br />work area to prevent damage.
<br />D.Provide protective coverings at walls,projections,jambs,sills,and soffits of openings.
<br />E.Protect finished floors,stairs,and other surfaces from traffic,dirt,wear,damage,or movement of
<br />heavy objects,by protecting with durable sheet materials.
<br />F.Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary,
<br />obtain recommendations for protection from waterproofing or roofing material manufacturer.
<br />G.Remove protective coverings when no longer needed;reuse or recycle coverings if possible.
<br />3.08 SYSTEM STARTUP
<br />A.Coordinate schedule for start-up of various equipment and systems.
<br />B.Verify that each piece of equipment or system has been checked for proper lubrication,drive
<br />rotation,belt tension,control sequence,and for conditions that may cause damage.
<br />C.Verify tests,meter readings,and specified electrical characteristics agree with those required by
<br />the equipment or system manufacturer.
<br />D.Verify that wiring and support components for equipment are complete and tested.
<br />E.Execute start-up under supervision of applicable Contractor personnel and manufacturer's
<br />representative in accordance with manufacturers'instructions.
<br />F.Submit a written report that equipment or system has been properly installed and is functioning
<br />correctly.
<br />3.09 DEMONSTRATION AND INSTRUCTION
<br />A.Demonstrate start-up,operation,control,adjustment,trouble-shooting,servicing,maintenance,
<br />and shutdown of each item of equipment at scheduled time,at equipment location.