Orange County NC Website
Revised 01/24 <br /> <br />ORANGE COUNTY <br /> CHANGE ORDER REQUEST <br />NORTH CAROLINA <br /> <br />______________________________________________________________________________________________________________ <br />Date: April 8, 2026 Project: Piedmont Food Processing Center HVAC Replacement Change Order No. 01 Department: Asset <br />Management Services Department Address: 306 Revere Road, Hillsborough NC 27278 Project: Piedmont Food Processing Center HVAC Replacement <br /> Contractor: Brady Service, Inc. Contractor Address: 2025 16th Street, Greensboro, NC 27405 Effective date of original contract: March 19, <br />2025 <br /> <br />This change order increases decreases the contract time by days. Check here if no impact to contract time . <br /> <br />Will this change order impact the date of substantial completion? Yes No. If yes, the amended date of substantial completion is: <br />_______________________________________________________________________________________________________________ <br /> <br />Full Description of Change: Piedmont Food Processing Center, provide and install two PC controllers for the existing Accurex Kitchen Hood systems. This <br />includes (1) EMS2 (EF1, DOAS2) 1 Accurex Kitchen Controls, Constant Volume/VFD for Exhaust Fan, and (1) EMS1 (EF1 DOAS1) 1 Accurex Kitchen <br />Controls, Constant Volume/VFD for Exhaust Fan. Provide and install new shunt trip breaker for dry kitchen to shut off electrical powe r when hood is <br />activated. <br /> <br />Reason for Change: The existing Accurex Kitchen hood system controllers do not support the new HVAC equipment. The controllers are required to s hut <br />down the heating, ventilation and cooling system when activated, the existing controllers do not perform this function. The m anufacturer provided <br />recommendations for wiring the existing controllers to perform this function, however, this did not work. The manufacturer pe rformed another site visit <br />and determined that new controllers would be required. The existing shunt trip breaker has failed and is not allowing the power to shutdown to the <br />existing kitchen equipment when the hood system is activated, therefore this breaker must be replaced to pass the final inspe ctions. <br />_______________________________________________________________________________________________________________ <br /> <br />Original contract sum: $ 375,000.00 <br /> <br />Contract sum prior to this change order: $ 375,000.00 <br /> <br />Amount of this change order: $ 37,055.00 <br /> <br />Total sum of the contract including this change order: $ 412,055.00 <br /> <br />_______________________________________________________________________________________________________________ <br />This change order is executed to amend the contract time or contract sum. It shall not be construed to impact the original contract, project, services, or <br />work in any other manner. All other terms of the Original Contract remain in effect. <br />Approved and executed this 8th day of April, 2026. <br />_______________________________ _____________________________ _____________________________ <br />Contractor Owner Architect (when retained) <br /> <br />By:____________________________ By:___________________________ By:___________________________ <br /> <br /> <br /> <br /> <br /> <br /> <br />Docusign Envelope ID: 048C1438-0C09-83D0-8069-7787E9608DD9 <br />4/9/2026 <br />Asst. Corporate Secretary <br />4/11/2026 <br />County Manager