<br /> <br />Page 4 of 10 <br /> <br />Brady will reuse existing breaker, conduit and conductors on line side. <br /> <br />Electrical connection to equipment will be made with short lengths of flexible "Liquid - Tite" <br />conduit. <br /> <br />All equipment has been selected for 208 volts, 60 hertz and 3 phase electrical service. <br /> <br />Brady will provide nameplates for identification of all equipment, motor starters and disconnect <br />switches. <br /> <br />Ductwork <br />Brady will furnish and install all supply ductwork and transitions needed to connect the new <br />AHU to the existing air distribution system. <br /> <br /> <br />Brady will furnish and install all return ductwork and transition as needed to connect the new <br />AHU to the existing ducted air return system. <br /> <br />Rectangular supply and return ductwork will meet the gauges and construction methods <br />indicated in the current ASHRAE guide and by SMACNA standards for the indicated <br />pressure classification. <br /> <br />Hanger and supports for all ductwork will be metal bands, angles and / or rods per ASHRAE <br />and SMACNA standards. <br /> <br />Pipe Insulation <br />Brady will insulate the refrigerant suction piping with ¾” armaflex insulation. <br /> <br />Crane and Rigging <br />Brady will furnish all crane, rigging, and trucking as needed for this project. <br /> <br />Upon receipt of equipment on the job site, Brady will inspect the unit for possible damage <br />during transit. This will include an inspection of unit exterior, all doors, access panels and <br />openings. If damage has occurred it will be immediately reported to the delivering carrier <br />and the damage noted on the receiving copy of the bill of lading. <br /> <br />Controls <br />Brady to furnish and install a programmable thermostat and low voltage wiring. <br /> <br />Air Balance <br />Brady excludes system air balancing for this project. The AHU air flow rate will be set per <br />the manufacturer’s specifications. <br /> <br />Start-Up <br />A Brady factory-authorized technician will perform start -up and inspection of the new split <br />system according to the manufacturers written instructions. <br /> <br />Clarifications <br />All work is based on straight time hours: Monday through Thursday from 7:00 am to 5:30 <br />pm. <br /> <br />Brady requires that the equipment for this project go through a submittal and review process <br />to verify equipment design and performance before the final order of equipment will be <br />released. This is completed to ensure that the end result meets the owner’s expectations. <br />Brady will request that you assign a company representative to review and sign off on the <br />equipment prior to order placement. <br />Docusign Envelope ID: B89C83AA-1E6D-4860-AB8B-87219C5E3EB4