<br /> FORM OF PROPOSAL
<br /> 1. MOBILIZATION - This work shall consist of furnishing all necessary insurance, coinsurance,
<br /> reinsurance, payment/performance bonds, local permits (including payment of permit fees),
<br /> mobilization of equipment, forces, and personnel for the project. Work shall also consist of
<br /> furnishing all necessary demobilization of equipment, forces, and personnel for the project. This
<br /> line item shall be a maximum of 3% of the base bid price. Payment for this line item will be made
<br /> under a one-time charge and will constitute full compensation for all labor, equipment, tools,
<br /> and other items necessary and incidental to the completion of this work.
<br /> 2. ATTENDANT BOOTHS PROCUREMENT AND DELIVERY WALNUT CHURCH GROVE—This work
<br /> shall consist of procurement and delivery of four(4) 6'x8'x8'Attendant Booths to the Walnut
<br /> Church Grove Waste& Recycling Center, Payment for this line item shall be made under a one-
<br /> time charge and will constitute full compensation for procurement and delivery of the booths
<br /> to the project sites.
<br /> 3. ATTENDANT BOOTH INSTALLATION WALNUT CHURCH GROVE—This work shadI consist of furnishing
<br /> all labor, material, equipment,tools and other items necessary and incidental to install four(4)
<br /> 6'x8'x8' Attendant Booths, install one (1) 8'x8'x8'x6"triangular concrete pad, and to install two (2)
<br /> bollards as indicated in the Drawings at the Walnut Church Grove Waste &. Recycling Center.
<br /> Installation shall also consist of furnishing all labor, material, equipment, tools, permitting and other
<br /> items necessary and incidental to install electrical connections, including conduit and fasters, to the
<br /> Attendant Booths. Installation shall also consist of furnishing all labor, material, equipment, tools,
<br /> permitting and other items necessary and incidental to ensure the booths are level and installed per
<br /> the manufacturer's instructions. Payment for this line item shall be made under a one-time charge and
<br /> will constitute full compensation for all labor, equipment,tools,and other items necessary and
<br /> incidental to the completion of the work.
<br /> 4. ATTENDANT BOOTHS PROCUREMENT AND DELIVERY EUBANKS ROAD—This work shall consist
<br /> of procurement and delivery of three (3) 6'x8'x8'Attendant Booths to the Eubanks Road Waste
<br /> &Recycling Center. Payment for this line item shall be made under a one-time charge and will
<br /> constitute full compensation for procurement and deliver of the booths to the project site.
<br /> S. ATTENDANT BOOTH INSTALLATION EUBANKS ROAD—This work shall consist of furnishing all labor,
<br /> material, equipment, tools and other items necessary and incidental to demolish and remove one (1)
<br /> existing Attendant Booth, and to install three (3) 6'x8'x8' Attendant Booths, install two (2) 8'x8'x8'x6"
<br /> triangular concrete pads, and to install six(6) bollards as indicated in the Drawings at the Eubanks
<br /> Road Waste & Recycling Center. Installation shall also consist of furnishing all labor, material,
<br /> equipment,tools, permitting and other items necessary and incidental to install electrical connections,
<br /> including conduit and fasters, to the Attendant Booths. Installation shall also consist of furnishing all
<br /> labor, material, equipment,tools, permitting and other items necessary and incidental to ensure the
<br /> booths are level and installed per the manufacturer's instructions. Payment for this line item shall be
<br /> made under a one-time charge and will constitute full compensation for all labor, equipment, tools,
<br /> and other items necessary and incidental to the completion of the work,
<br /> Attendant Booth Additions TRC PN: 670493
<br /> Orange County, North Carolina Addendum #3 -SEPTEMBER 2025
<br /> BF-3
<br />
|