9 <br /> 13 <br /> TIMELINE <br /> 2019 ✓ Orange County SIM Workshop identifies gaps and action items (April 2019). <br /> ✓ Crisis-Diversion Facility recommended to and endorsed by BOCC (April <br /> 2021 ). <br /> ✓ Preliminary facility design and cost estimation completed (early 2023). <br /> ✓ Site location and land purchase (June 30, 2025). <br /> • Final facility architectural design work (4Q2025). <br /> • Construction Documents/Permitting/Bid/GMP Approval (2Q 2026). <br /> 2027 • Construction complete (2Q 2027). <br /> • CDF start up and begin operation (3Q 2027). <br />