<br /> Chair Bedford said they do not need to decide on the gym part and that can be part of
<br /> the design and discussions with Mebane.
<br /> Slide #30
<br /> Recommended School Capital Funding
<br /> • Pre-Design Maps of School Projects
<br /> Carrboro Elementary OCS Proposed Elementary
<br /> t 'I
<br /> r ,
<br /> 1
<br /> �Nt)K I H UA Rt LI NA
<br /> Slide #31
<br /> Recommended School Capital Funding
<br /> Major Projects are funded using a combination of Pay-Go and Bond Funds.
<br /> CHCCS Projects Bond Funds Pay-Go Funds Total Funds OCS Projects Bond Funds Pay-Go runds Total Funds
<br /> Carrboro Elementary $ 47,700,000 $ 5,300,000 $ 53,000,000 Elementary Replacement 1 $ 57,283,000 $ 2,817,000 $ 60,100,000
<br /> Estes Hills Elementary$ 51,547,000 $11,283,000 $ 62,830,000 Major Elementary Renovation $ 27,000,000 $ 3,000,000 $ 30,000,000
<br /> Frank Porter Graham $ 63,901,300 $ 6,240,000 $ 70,141,300 Major Middle School Renovation $ 37,340,000 $ 7,660,000 $ 45,000,000
<br /> Contingency+HPN $ 11,551,700 $31,050,999 $ 42,602,699 Contingency+HPN $ 3,677,000 $22,649,001 $ 26,326,001
<br /> Total $174,700,000 $53,873,999 $228,573,999 Total $125,300,000 $36,126,001 $161,426,001
<br /> Pay-Go funds provide four major uses to support the Bond Program:
<br /> - Absorb soft costs like Design, Project Management
<br /> • Project Management included in separate$1 M/year project not allocated to either district
<br /> - Extend project budgets above what the Bond could support on its own.
<br /> - Improve County debt metrics once county debt exceeds 15% of GF revenues
<br /> - Once bond projects are done, support the districts'High Priority Needs
<br /> ORANGE COUNTY
<br /> 31 NORTH CAROLINA