Orange County NC Website
Page 9 of 53 <br />5-2-25 <br /> <br />5.5. The CMAR-GMP Contingency may be applied to any items within the Cost of the Work without <br />the necessity of a change order, without constituting a change in the Work, and without resulting in <br />any change in the GMP. The CMAR will notify the Owner and Project Designer in writing of the <br />CMAR’s intent to apply any part of the CMAR-GMP Contingency to any item within the Cost of <br />the Work prior to any such application. The CMAR shall fully document the change on its copy of <br />the Construction Documents for inclusion in the as-built record documents required by this <br />Contract. <br />5.6. Unless otherwise agreed by the Owner, and provided that the Total Construction Budget remains <br />$TBD, the total CMAR-GMP Contingency for the Project shall not exceed $TBD. If the Owner <br />changes the Total Construction Budget, the CMAR-GMP Contingency shall not exceed four <br />percent (4.0%), as a value line item of the sum of the Cost of the Work and the CMAR General <br />Conditions, all as more fully defined in this Contract, as of the date when the final GMP is <br />established and approved by the Owner, subject to modification and limitation as set forth herein. <br />When each GMP is fixed, the CMAR-GMP Contingency for that GMP shall be converted to a <br />lump sum. The entire CMAR Contingency shall be fixed in the final GMP, based on the Total <br />Construction Budget at the time of the final GMP, after which the CMAR Contingency shall not be <br />adjusted unless an amount is negotiated with Owner requested Change Orders to the Work of the <br />Project. <br />5.7. The amount of the CMAR-GMP Contingency is to be reviewed by the Owner as part of its review <br />of each GMP. The Owner retains the right to specifically request revisions to the amount of the <br />CMAR-GMP Contingency prior to the Owner’s acceptance and approval of each GMP. If, after a <br />contingency is fixed as part of a GMP proposal, the contract prices are lower than anticipated, the <br />CMAR and Owner agree that the CMAR-GMP Contingency shall not be reduced prior to <br />completion of that GMP phase. In the event that the CMAR is not required to use any or all of the <br />CMAR-GMP Contingency for a particular GMP it shall be carried forward to each subsequent <br />GMP. After final completion of the Project, the Owner shall pay the CMAR Thirty percent (30%) <br />of the unused CMAR-GMP Contingency. In the event that there are any funds remaining in any <br />special or dedicated Owner’s allowance, those funds shall be retained solely by the Owner. <br />6. PROJECT DESIGNER’S STATUS <br /> <br />6.1. The Project Designer shall provide liaison and necessary inspection of the Work to ensure <br />compliance with the Construction Documents. The Project Designer is the agent of the Owner only <br />for the purposes and to the extent stipulated in the various Contract Documents. The Project <br />Designer has authority to stop Work or to order Work removed, or to order corrections of faulty or <br />non-compliant Work where such action may be necessary to assure successful completion of the <br />Work. <br /> <br />6.2. The Project Designer is the impartial interpreter of the Contract Documents, and, as such, shall <br />exercise its powers under the Contract to enforce faithful performance by both the Owner and the <br />CMAR, taking sides with neither. <br /> <br />6.3. Should the Project Designer cease to be employed on the Project for any reason whatsoever, then <br />the Owner shall employ a competent replacement who shall assume the status of the former Project <br />Designer. <br /> <br />6.4. The Project Designer will make periodic inspections of the Project at intervals appropriate to the <br />stage of construction. The Project Designer will inspect the progress, the quality and the quantity of <br />the Work and shall verify work in place for purposes of payment and verification of payment <br />applications. <br /> <br />6.5. The Project Designer and the Owner shall have access to the Work whenever it is in preparation <br />and progress during normal working hours. The CMAR shall provide facilities for such access so <br />the Project Designer may perform its functions under the Contract Documents. <br /> <br />Docusign Envelope ID: 5A9E3BC2-EAE1-4C35-82D9-B4D6A375FA78