Page 27 of 53 <br />5-2-25 <br /> <br />(NTP), the CMAR shall submit a preliminary CPM schedule for inclusion in the contract bid <br />packages consistent with the time frames submitted in each GMP. <br /> <br />25.7. After contract award but prior to thirty (30) days from the date of the notice to proceed, the CMAR <br />shall obtain from the Subcontractors their respective Work activities and integrate them into a <br />Project construction schedule. The CMAR shall develop the complete and final CPM schedule in <br />the form of a CPM network arrow diagram using the CMAR’s logic and time estimates for each <br />segment of the Work and manpower loaded to complete the Work within the scheduled time <br />frames. The scheduling obligation shall include tracking the progress of the Owner’s and Project <br />Designer’s tasks and activities in relation to the milestone schedule and promptly notifying Owner <br />of any delay that might impact construction. The CMAR shall make recommendations to the <br />Owner, with a copy to the Project Designer, regarding strategies for overcoming any delay in the <br />design of the Project that will affect the construction schedule. The CMAR and the Project <br />Designer shall prepare, if deemed necessary, a schedule fixing dates upon which foreseeable <br />clarifications will be required. The schedule will be subject to addition or change in accordance <br />with progress of the Work. The Project Designer shall furnish drawings or clarifications in <br />accordance with that schedule. The CMAR shall not proceed with the Work without such detail <br />drawings and/or written clarifications. <br /> <br />25.8. The arrow network diagram will be drawn in a level of detail suitable for display of salient features <br />of the Work, including but not limited to the placing of orders for materials, submission of shop <br />drawings for approval, approval of shop drawings by the Project Designer and the Owner, delivery <br />of material, and all Work activities inclusive of punch list agreed to by the Owner. Each Work <br />activity shall be assigned a time estimate by the CMAR. One-day shall be the smallest time unit <br />used. Data shall also be provided in Gantt form. This schedule will not be the basis for invoicing, <br />but may be considered by the Design Professional and the Owner when evaluating the percentage <br />of Work represented to be complete in each schedule of values. <br /> <br />25.9. Upon completion of the network diagrams, the CMAR shall have computer input data prepared, <br />and a computer run made to generate a printout for the Project based on the information supplied. <br />In the event the completion date indicated by the schedule exceeds the contractual date, the logic <br />and time estimates used to develop the plan will be reviewed, changes made in the logic and time <br />estimates, and another computer run made to generate a new schedule. This procedure shall be <br />repeated, if necessary, to provide a plan and schedule to meet Owner requirements. All submissions <br />shall be both in hard copy and in electronic format. <br />25.10. Within fifteen (15) days of each GMP notice to proceed, the updated CPM schedule shall be <br />submitted to the Owner for review and approval. No application for payment will be processed <br />until the Project CPM schedule is approved by the Owner. This working plan shall show job <br />identification, job duration, manpower loading, cost loading, calendar dates for start and finish of <br />each job, and jobs critical to the completion of the Project on schedule. When approved by the <br />Owner, they shall become the working plan and schedule for the Project and such information shall <br />be provided to the Contractor for distribution to the Project Team. The CMAR shall distribute to <br />the Subcontractors the approved Project CPM schedule and shall display same at the job site. <br /> <br />25.11. The CMAR shall review the plan and schedule each week. An updated Project schedule shall be <br />furnished showing actual completed Work at the end of each month in respect to the entire Project. <br />The form used shall be approved by the Owner and shall be submitted with the monthly invoice. <br />The CMAR shall also develop and submit a Work plan for a two week, thirty day and sixty day <br />look ahead. <br /> <br />25.12. The CMAR shall provide regular monitoring of the schedule as construction progresses, identify <br />potential variances between scheduled and desired completion dates, review the schedule for Work <br />not started or incomplete, review the status of submittals and delivery of long-lead time deliveries, <br />review the Owner’s occupancy priorities, and take the action necessary to meet the required <br />Docusign Envelope ID: 5A9E3BC2-EAE1-4C35-82D9-B4D6A375FA78