Page | 28 <br />Revised 12/24 <br /> <br />estimates, and another computer run made to generate a new schedule. This procedure shall be <br />repeated, if necessary, to provide a plan and schedule to meet Owner requirements. All submissions <br />shall be both in hard copy and in electronic format. <br />25.10. Within fifteen (15) days of each GMP notice to proceed, the updated CPM schedule shall be <br />submitted to the Owner for review and approval. No application for payment will be processed <br />until the Project CPM schedule is approved by the Owner. This working plan shal l show job <br />identification, job duration, manpower loading, cost loading, calendar dates for start and finish of <br />each job, and jobs critical to the completion of the Project on schedule. When approved by the <br />Owner, they shall become the working plan and sch edule for the Project and such information shall <br />be provided to the Contractor for distribution to the Project Team. The CMAR shall distribute to <br />the Subcontractors the approved Project CPM schedule and shall display same at the job site. <br /> <br />25.11. The CMAR shall review the plan and schedule each week. An updated Project schedule shall be <br />furnished showing actual completed Work at the end of each month in respect to the entire Project. <br />The form used shall be approved by the Owner and shall be submitted with the monthly invoice. <br />The CMAR shall also develop and submit a Work plan for a two week, thirty day and sixty day <br />look ahead. <br /> <br />25.12. The CMAR shall provide regular monitoring of the schedule as construction progresses, identify <br />potential variances between scheduled and desired completion dates, review the schedule for Work <br />not started or incomplete, review the status of submittals and delivery of long -lead time deliveries, <br />review the Owner’s occupancy priorities, and take the action necessary to meet the required <br />completion date. The CMAR shall furnish to the Owner various schedules and updates setting forth <br />planned and completed progress of the Project broken down by the various divisions or parts of the <br />Work and by calendar days. The CMAR shall ensure t hat all schedules are prepared and updated in <br />strict conformance with the Owner’s requirements for formatting of reports for the Owner. The <br />CMAR shall keep the Owner, the Project Designer and all Subcontractors fully informed as to all <br />changes and updates to the schedule. The CMAR shall ensure that all schedules are prepared and <br />updated in strict conformance with the Owner’s requirements and for provision of one inclusive <br />schedule incorporating necessary lead times for actions required, by the Owner and reg ulatory <br />agencies (including Orange County), by the Consultant, by the CMAR, and by utility companies <br />providing services or relocating service lines and facilities, by all Subcontractors, and for <br />significant General Condition’s activities, including but not limited to agenda submittals, permit <br />and approvals applications and review of interim and final plans, specifications and bid packages. <br />25.13. The CMAR shall schedule and preside over regular site coordination meetings with Subcontractors <br />as conditions on the Project require, but at least weekly. In addition, the CMAR shall conduct <br />weekly progress meetings and other meetings as may be directed by the Owner, at which <br />Subcontractors, the Owner, the Project Designer, other designated representatives, and the CMAR <br />can discuss jointly such matters as progress, scheduling, and construction-related problems. All <br />Subcontractors shall be represented at these job progress conferences by both home office and <br />Project personnel, unless specifically excused by both the CMAR and the Owner. The CMAR shall <br />require attendance from other subcontractors and material suppliers who can contribute toward <br />maintaining required job progress. It shall be the principal purpose of these meetings, or <br />conferences, to effect coordination, cooperation and assistance in every practical way toward the <br />end of maintaining progress of the Project on schedule and to complete the Project within the <br />specified contract time. The CMAR shall be prepared to assess progress of the Work and to <br />recommend remedial measures for correction of progress as may be appropriate. The CMAR with <br />assistance from the Project Designer shall be the coordinator of the conferences and shall preside as <br />chairman. The CMAR shall take and distribute complete minutes of meetings to all attendees and <br />others as directed by the Owner within three (3) days of such meetings. Representatives of the <br />Owner may attend any or all meetings and shall in any case receive all notices and minutes of <br />meetings. <br /> <br />25.14. The CMAR shall keep accurate and detailed written records of Project progress during all stages of <br />construction. The CMAR shall maintain a detailed daily diary of all events, which occur at the <br />Docusign Envelope ID: 5A9E3BC2-EAE1-4C35-82D9-B4D6A375FA78