4 <br />Submit Engineering Construction Documents tc Construction Time 0 <br />Lcans and Grants Section for review/approval (12/19/2005) <br />Advertise far Construction Bids Time 0 + 2 weeks <br />(1 /03/2006) <br />Open Bids Time 0 + 4 weeks <br />contract to BOCC for approval (1/31/2006) <br />Awazd Bids Time 0 + 4.2 weeks <br />(2/07/2006) <br />Notice to Proceed Time 0 + 4.2 weeks <br />(2/08/2006) <br />Complete waterline constructicn Time 0 +3 months <br />(4/08/2006) <br />Complete waterline testing, retesting, repairs (if required) Time 0 + 4 months <br />Chlorination (disinfection), put in service (5/08/2006) <br />Complete pumping station/sewer line construction EDD area Time 0 + 6 months <br />(6/23/2006) <br />Complete pumping station/sewer line testing, servicing, etc„ Time 0 + 6.5 months <br />EDD area (6/23/2006) <br />Complete sewer line construction north Buckhorn Community Time 0 + 7,5 months <br />(7/23/2006) <br />