OC Sportsplex Pool HVAC Unit Replacement <br />PDC Project 23022 Commissioning of HVAC 23 08 00 - 1 <br />SECTION 23 08 00 <br />COMMISSIONING OF HVAC <br />PART 1 GENERAL <br />1.01 SUMMARY <br />A.This section covers the Contractor's responsibilities for commissioning;each subcontractor or <br />installer responsible for the installation of a particular system or equipment item to be <br />commissioned is responsible for the commissioning activities relating to that system or equipment <br />item. <br />B.The Commissioning Authority (CA)directs and coordinates all commissioning activities and <br />provides Prefunctional Checklists and Functional Test Procedures for Contractor's use. <br />C.The entire HVAC system is to be commissioned,including commissioning activities for the <br />following specific items: <br />1.Control system. <br />2.Major and minor equipment items. <br />3.Piping systems and equipment. <br />4.Ductwork and accessories. <br />5.Variable frequency drives. <br />6.Other equipment and systems explicitly identified elsewhere in Contract Documents as <br />requiring commissioning. <br />D.The Prefunctional Checklist and Functional Test requirements specified in this section are in <br />addition to,not a substitute for,inspection or testing specified in other sections. <br />1.02 REFERENCE STANDARDS <br />A.ASHRAE Guideline 1.1 -HVAC&R Technical Requirements for the Commissioning Process;2007, <br />with Errata (2012). <br />1.03 SUBMITTALS <br />A.Updated Submittals: Keep the Commissioning Authority informed of all changes to control system <br />documentation made during programming and setup;revise and resubmit when substantial <br />changes are made. <br />1.System name. <br />2.List of devices. <br />3.Step-by-step procedures for testing each controller after installation,including: <br />a.Process of verifying proper hardware and wiring installation. <br />b.Process of downloading programs to local controllers and verifying that they are <br />addressed correctly. <br />c.Process of performing operational checks of each controlled component. <br />d.Plan and process for calibrating valve and damper actuators and all sensors. <br />e.Description of the expected field adjustments for transmitters,controllers and control <br />actuators should control responses fall outside of expected values. <br />B.Startup Reports,Prefunctional Checklists,and Trend Logs: Submit for approval of Commissioning <br />Authority. <br />C.HVAC Control System O&M Manual Requirements. In addition to documentation specified <br />elsewhere,compile and organize at minimum the following data on the control system: <br />1.Specific step-by-step instructions on how to perform and apply all functions,features,modes, <br />etc.mentioned in the controls training sections of this specification and other features of this <br />system. Provide an index and clear table of contents. Include the detailed technical manual <br />for programming and customizing control loops and algorithms. <br />2.Full as-built set of control drawings. <br />3.Full as-built sequence of operations for each piece of equipment. <br />4.Full points list;in addition to the information on the original points list submittal,include a <br />listing of all rooms with the following information for each room: <br />a.Floor. <br />Docusign Envelope ID: D4F3B98E-0756-4A0C-A3AD-05AA32D39F1C