<br /> <br />Page 7 of 14 <br /> <br />vacuum pump to evacuate and dehydrated the refrigeration system until the system has been <br />evacuated to 500 microns and held for four hours. <br /> <br />Brady will charge the refrigerant piping system to meet the manufacturer’s specifications. <br /> <br /> <br />Electrical <br />Brady will replace existing disconnect, conduit and conductors required for load side electrical <br />service from point of existing disconnect to the new AHU and condensing unit. Disconnect, <br />conduit and conductors will be sized per the NEC and based on the AHU and condensing unit <br />MOP and MCA provided to Brady by the equipment manufacturer. <br /> <br />Brady will reuse existing breaker, conduit and conductors on line side. <br /> <br />Brady has identified physical space in panel for a new amp breaker to feed the new AHU <br />and condensing unit. However The electrical load of the panel has not been verified to <br />handle the load of the new AHU and condensing unit. <br /> <br />Electrical connection to equipment will be made with short lengths of flexible "Liquid - Tite" <br />conduit. <br /> <br />All equipment has been selected for 208 volts, 60 hertz and 3 phase electrical service. <br /> <br />Brady will provide nameplates for identification of all equipment, motor starters and disconnect <br />switches. <br /> <br />Pipe Insulation <br />Brady will insulate the refrigerant suction piping with ¾” armaflex insulation. <br /> <br />Crane and Rigging <br />Brady will furnish all crane, rigging, and trucking as needed for this project. <br /> <br />Upon receipt of equipment on the job site, Brady will inspect the unit for possible damage <br />during transit. This will include an inspection of unit exterior, all doors, access panels and <br />openings. If damage has occurred it will be immediately reported to the delivering carrier <br />and the damage noted on the receiving copy of the bill of lading. <br /> <br />Controls <br />Brady to furnish and install a programmable thermostat and low voltage wiring. Brady will <br />provide new Equipment with BACnet Cards. Controls integration in not included in this <br />proposal (owner will contract directly with Siemens for Controls work). <br /> <br />Air Balance <br />Brady excludes system air balancing for this project. The AHU air flow rate will be set per <br />the manufacturer’s specifications. <br /> <br />Start-Up <br />A Brady factory-authorized technician will perform start-up and inspection of the new split <br />system according to the manufacturers written instructions. <br />Docusign Envelope ID: 33B9741C-8E15-46BC-9277-7C5A263BA05E