8 <br />Revised 01/24 <br />ARTICLE 8 <br />RESPONSIBILITIES OF THE OWNER <br />8.1 Cooperation and Coordination <br />8.1.1 The Owner shall meet with the Designer as necessary at mutually convenient times to provide information necessary to enable the Designer to <br />develop a detailed written analysis and complete needs summary of the Project. <br />8.1.2 The Owner shall examine documents submitted by the Designer and shall make reasonable efforts to render decisions pertaining thereto no <br />later than the dates specified in the schedule for such decisions described in Article 6.1.2. <br />8.1.3 Angel Barnes, Capital Projects Manager shall be the Owner's Construction Projects Administrator and shall act in the Owner's behalf and as its <br />representative with respect to the Project and shall have the authority to render decisions and approve changes in the scope of the Project within <br />guidelines established by the County Manager and the Board of County Commissioners and shall be available during working hours as often as may be <br />reasonably required to render decisions and to furnish information. Owner may replace the individual serving as Construction Projects Administrator at <br />any time. Should such replacement occur Designer will be so informed within a reasonable time. <br />8.2 Surveys and Testing <br />8.2.1 The Owner shall furnish the Designer with a certified land survey of the site, giving, as applicable, grades and lines of streets, alleys, pavements <br />and adjoining property; rights-of-way, restrictions, easements, encroachments, zoning, deed restrictions, boundaries and contours of the site; locations, <br />dimensions and complete data pertaining to existing buildings, other improvements and trees, and other pertinent information reasonably requested by <br />the Designer including that concerning available service and utility lines, both public and private, above and below grade, including inverts. <br />8.2.2 The Owner shall provide the services of a geotechnical engineer or other consultant, or compensate for such sub-consultant services provided by <br />the Designer, when such services are reasonably deemed necessary by the Designer, and agreed and consented to in writing by Owner, as shown on the <br />Designer's schedule described in Article 6.1.2, to provide reports, test borings, test pits, soil bearing values, percolation tests, air and water pollution <br />tests, ground corrosion and resistivity tests and other necessary operations for determining subsoil, air and water conditions, all together with reports <br />and appropriate professional recommendations thereof to ensure construction materials and geotechnical requirements of the construction contract <br />are met. <br />8.2.3 All services, data, information, surveys and reports required of the Owner pursuant to this Article 8, shall be furnished at the Owner's expense <br />and, absent any negligence or failure to follow professional standards on the part of Designer, the Designer shall be entitled to rely upon the accuracy <br />and completeness of such services, data, information, surveys and reports. <br />8.3 Permits and Approvals <br />8.3.1 The Owner shall secure and pay for all necessary permits, licenses, approvals, easements, assessments, and charges required for the <br />construction, use or occupancy of permanent structures or for permanent changes in existing facilities. The Designer shall provide the Owner with a <br />schedule of all required approvals and of the dates by which application for such approvals must be made in order to avoid any risk of delay to the <br />Project, prepare necessary application forms, present documents requiring approval by the Owner and submit documents with the Owner's approval to <br />the appropriate approval agency. <br />ARTICLE 9 <br />INSURANCE <br />9.1 General Requirements <br />Docusign Envelope ID: 76D66578-87F7-42C9-862F-5B1BD878A8F6