29 <br />Revised 01/24 <br />in taking any such action shall be charged to the Contractor and deducted from any amounts <br />remaining due under the Agreement. <br /> <br />13.13 The Contractor may be entitled to an extension of the Contract Time (but no increase in <br />the Contract Sum) for delays arising from unforeseen causes beyond the control and without the <br />fault or negligence of the Owner, the Contractor or the Contractor’s Subcontractors as follows: <br /> <br />a) Labor disputes and strikes that directly impact the critical path activities of the Contract <br />Construction Schedule; <br /> <br />b) Acts of God, tornado, fire, hurricane, blizzard, earthquake, typhoon, or flood that damage <br />completed Work or stored materials. <br /> <br />c) Acts of the public enemy; acts of the State, Federal, or local government in their sovereign <br />capacities. <br /> <br />d) Abnormal inclement weather as defined in Article 13.14. <br /> <br />13.14 On any day that the Contractor considers that the Project is delayed by adverse weather <br />conditions, the Contractor shall identify in writing to the Designer and the Owner the adverse <br />weather conditions affecting each activity, the specific nature of the activity affected, the number <br />of hours lost, and the number of and identity (by responsibility or trade) of workers affected and <br />shall obtain from the Designer written recognition of the delay. The time for performance of this <br />Contract includes an allowance for a number of calendar days which may not be suitable for <br />construction Work by reason of adverse weather. The Contract Time will be extended only if the <br />number of calendar days of adverse weather recognized by the Designer exceeds the number <br />of inclement weather days set forth below, and the Contractor demonstrates how this adverse <br />weather impacts activities on the critical path of the Contract Construction Schedule. Month <br />Number of Inclement Weather Days <br /> January 10 <br /> February 10 <br /> March 10 <br /> April 9 <br /> May 10 <br /> June 9 <br /> July 11 <br /> August 10 <br /> September 8 <br /> October 7 <br /> November 8 <br /> December 9 <br /> <br />13.15 If the Contractor believes that the progress of the Work has been adversely affected by <br />adverse weather recognized by the Designer during a particular month, the Contractor shall <br />submit a written request for extension of time to the Designer. Such a request for time extension <br />of the Contract Time shall be submitted by the tenth (10th) day of the month following that <br />month in which the adverse weather is encountered. The request shall include, but is not limited <br />to, the following information: a) Detailed description of weather's effect on scheduled activities <br />and its net effect on the critical path of the Project, and b) Weather records from the official <br />weather station nearest the Project site and records of actual observation as contained in daily <br />reports, correspondence, or other documentation. <br />Docusign Envelope ID: EF9C08D2-5B75-438B-8D6D-8473F81BD7C4