28 <br /> <br />Revised 01/24 <br /> <br />will be performed simultaneously and sequentially with the performance of the Work by the <br />Contractor. It shall be necessary for the Contractor to coordinate construction activities with <br />such other contractors, particularly with respect to access to work areas, storage of materials, <br />and use of elevators and other common facilities. The Contractor shall diligently and in good <br />faith cooperate with the Owner, the Designer, and all other contractors with respect to such <br />matters and shall regularly and faithfully attend any and all meetings called by the Owner or the <br />Designer with respect to such matters. Any disputes between the Contractor and any other <br />separate prime contractor with respect to such matters shall be resolved in accordance with the <br />claim and dispute resolution procedures in the Agreement. <br /> <br />ARTICLE 13. CONTRACT TIME <br /> <br />13.1 Within fourteen (14) days after receipt of the Construction Contract by the Contractor for <br />signatures, the Project Expediter shall prepare and submit to the Designer and Owner for review <br />and approval a preliminary progress schedule for the Work pursuant to the requirements stated <br />in the Contract Documents. <br /> <br />13.2 Within fourteen (14) days after initial receipt of the Construction Contract for signatures the <br />Contractor shall submit to the Designer a Submittal Register listing all Submittals the Contractor <br />is required to make or proposes to make under the Contract Documents, the dates on which the <br />Contractor proposes to make such Submittals and the dates by which the Contractor reasonably <br />requires a response from the Designer with respect to each Submittal. The dates submitted <br />shall be incorporated into the Contract Construction Schedule as Completion Dates when they <br />have been approved or modified by the Owner. The Designer shall not be required to review <br />any Submittal from the Contractor until a Submittal Register acceptable to and approved by the <br />Owner has been submitted by the Contractor. <br /> <br />13.3 Not later than thirty (30) days following execution and delivery of the Construction <br />Agreement by Owner to Contractor, the Owner shall deliver to the Contractor a Notice to <br />Proceed. The Notice to Proceed shall state a commencement date on which it is expected that <br />the Contractor will begin the Work to be performed under the Agreement. The Contract Time <br />shall be measured from said specified commencement date. The commencement date stated in <br />the Notice to Proceed shall not be earlier than three (3) days after the Notice to Proceed is <br />served on the Contractor. <br /> <br />If, other than by mutual agreement, said specified commencement date is more than thirty (30) <br />days after the date of execution and delivery of the Agreement from Owner to Contractor and <br />the Contractor believes said delay justifies an increase in Contract Price or an extension of <br />Contract Time, the Contractor may make a claim therefore as provided in Article 14 or Article <br />15. No Work shall be done prior to the date specified in the Notice to Proceed. A final Contract <br />Construction Schedule shall be submitted for approval by the Contractor, Designer, and Owner <br />no later than fourteen (14) days after Notice to Proceed. No payments shall be due the <br />Contractor until this schedule is approved by all parties. <br /> <br />13.4 The Contract Construction Schedule is a Contract Document. The Contractor represents <br />that the Contract Construction Schedule has been reviewed in detail, that the Contractor <br />participated in its preparation, that all of the activities which impact, limit, or otherwise affect the <br />time of completion of the Work are shown in the Contract Construction Schedule and that all of <br />the activities of others which impact, limit, or otherwise affect the start, duration, or completion of <br />Docusign Envelope ID: 687B9CC7-F1BC-43DB-A291-A8D859EFA3B2