36 <br /> Schedule for Construction/Development <br /> The project is proposed to begin construction upon proper permitting. The development of the <br /> property will consist of the clearing of trees within the work area and disturbance limits, <br /> followed by minimal grading, the installation of the property well, the construction of the <br /> necessary structures including the office, shed, caretakers quarters and supporting facilities. <br /> Upon completion of this phase, the on-site wastewater system will be constructed followed by <br /> the placement of the necessary gravel and driveway access will be completed. <br />