9/2/2020 <br /> <br /> 013200 - 1 <br />SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION <br />PART 1 - GENERAL <br />1.1 RELATED DOCUMENTS <br />A. Drawings and general provisions of the Contract, including General and Supplementary <br />Conditions and other Division 01 Specification Sections, apply to this Section. <br />1.2 SUMMARY <br />A. Section includes administrative and procedural requirements for documenting the progress of <br />construction during performance of the Work, including the following: <br />1. Contractor's construction schedule. <br />2. Construction schedule updating reports. <br />3. Daily construction reports. <br />4. Site condition reports. <br />5. Special reports. <br />B. Related Requirements: <br />1. Section 013300 "Submittal Procedures" for submitting schedules and reports. <br />2. Section 014000 "Quality Requirements" for submitting a schedule of tests and inspections. <br />1.3 DEFINITIONS <br />A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, <br />and controlling the construction project. Activities included in a construction schedule consume <br />time and resources. <br />1. Critical Activity: An activity on the critical path that must start and finish on the planned <br />early start and finish times. <br />2. Predecessor Activity: An activity that precedes another activity in the network. <br />3. Successor Activity: An activity that follows another activity in the network. <br />B. Cost Loading: The allocation of the schedule of values for the completion of an activity as <br />scheduled. The sum of costs for all activities must equal the total Contract Sum unless otherwise <br />approved by Architect. <br />C. CPM: Critical path method, which is a method of planning and scheduling a construction project <br />where activities are arranged based on activity relationships. Network calculations determine <br />when activities can be performed and the critical path of Project. <br />D. Critical Path: The longest connected chain of interdependent activities through the network <br />schedule that establishes the minimum overall Project duration and contains no float. <br />DocuSign Envelope ID: 7D9ACD4F-8F6C-42B6-9ADB-C60032DB6D03