9/2/2020 <br /> <br /> 012600 - 2 <br />e. Quotation Form: Use forms acceptable to Architect. <br />B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the <br />Contract, Contractor may initiate a claim by submitting a request for a change to Architect. <br />1. Include a statement outlining reasons for the change and the effect of the change on the <br />Work. Provide a complete description of the proposed change. Indicate the effect of the <br />proposed change on the Contract Sum and the Contract Time. <br />2. Include a list of quantities of products required or eliminated and unit costs, with total <br />amount of purchases and credits to be made. If requested, furnish survey data to <br />substantiate quantities. <br />3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade <br />discounts. <br />4. Include costs of labor and supervision directly attributable to the change. <br />5. Include an updated Contractor's construction schedule that indicates the effect of the <br />change, including, but not limited to, changes in activity duration, start and finish times, <br />and activity relationship. Use available total float before requesting an extension of the <br />Contract Time. <br />6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed <br />change requires substitution of one product or system for product or system specified. <br />7. Proposal Request Form: Use form acceptable to Architect. <br />8. Indicate Contractor Overhead & Profit, combined amount not to exceed 10%. Sub- <br />Contractor Overhead and fees not to exceed 5% <br />1.5 ADMINISTRATIVE CHANGE ORDERS <br />A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for <br />preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of <br />allowances. <br />1.6 CHANGE ORDER PROCEDURES <br />A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order <br />for signatures of Owner and Contractor on AIA Document G701. <br />1. Contractor may charge up to 10% Overhead and Profit. <br />2. Sub mark-ups will not exceed 5% Overhead and Profit. <br />1.7 CONSTRUCTION CHANGE DIRECTIVE <br />A. Construction Change Directive: Architect may issue a Construction Change Directive. <br />Construction Change Directive instructs Contractor to proceed with a change in the Work, for <br />subsequent inclusion in a Change Order. <br />1. Construction Change Directive contains a complete description of change in the Work. It <br />also designates method to be followed to determine change in the Contract Sum or the <br />Contract Time. <br />DocuSign Envelope ID: 7D9ACD4F-8F6C-42B6-9ADB-C60032DB6D03