19 Orange County Comprehensive Land Use Plan <br />Project Cost <br /> <br /> Phase 1 Launch Project (Month 1) Phase Total: $ 26,405 <br /> 1.1 Kickoff Meeting with County Staff Planning Team <br /> 1.2 Kickoff Meeting with Staff Working Group <br /> 1.3 Stakeholder Interviews (including BOCC members) <br /> 1.4 Reconnaissance Trip with County Staff Team <br /> 1.5 Develop Project Management Plan <br /> 1.6: Collect and Inventory ArcGIS Data, Policy Documents, and Relevant Studies <br /> 1.7: Develop Public Engagement Branding <br /> Project Management Meetings <br /> Total Travel <br /> Phase 2 Identify New Issues and Opportunities (Months 2-7) Phase Total: $ 40,261 <br /> 2.1 Develop Current Policy Profile <br /> 2.2 Staff Working Group Meetings #2-#5 <br /> 2.3 Briefing to Board of County Commissioners <br /> 2.4 Prepare Equity Database <br /> 2.5: Community Engagement Window #1: Confirming Community Aspirations <br /> 2.6 Summary of New Issues and Opportunities <br /> 2.7 Briefings to the Planning Board and Board of County Commissioners <br /> Project Management Meetings <br /> Total Travel <br /> Phase 3: Evaluate Planning Influences (Months 3-8) Phase Total: $ 17,508 <br /> 3.1 Develop the Factbook <br /> 3.2 Staff Working Group Meeting #6 <br /> Project Management Meetings <br /> Total Travel <br /> Phase 4: Develop Plan (Months 9-20) Phase Total: $ 86,630 <br /> 4.1 Develop Draft Plan Framework, Vision, and Goals <br /> 4.2 Project Team Work Session - Growth and Conservation Framework <br /> 4.3 Development of Land Use & Development Recommendations Report <br /> 4.4 Briefing to Board of Commissioners <br /> 4.5 Develop Plan Policies and Actions <br /> 4.6 Staff Working Group Meetings #7-15 <br /> 4.7 Community Engagement Window #2 - Testing Growth and Conservation Framework <br /> 4.8 Briefings to Planning Board and Board of County Commissioners <br /> 4.9 Prepare Public Review Draft of Comprehensive Land Use Plan <br /> 4.10 Community Engagement Window #3 - Unveiling of Draft Plan <br /> 4.11 Briefing to Board of Commissioners <br /> Project Management Meetings <br /> Total Travel <br /> Phase 5: Adopt Plan (Months 21-26) Phase Total: $ 16,379 <br /> 5.1: Finalize Public Hearing Draft of Comprehensive Land Use Plan <br /> 5.2: Staff Working Group Meeting #16 <br /> 5.3: Public Hearings with Planning Board and Board of County Commissioners (up to 2) <br /> 5.4: Finalize the Adopted Comprehensive Plan and Transmit All Final Files to County Staff <br />Team <br /> Project Management Meetings <br /> Total Travel <br /> Konveio Public Engagement Platform License <br /> Contingency Budget for Board of Commissioner Meetings (up to 2) <br /> Budget for Targeted Public Engagement Meetings <br /> GRAND TOTAL <br />Meetings with BOCC <br /> $ 6,690 <br /> $ 3,398 <br /> $ 2,270 <br /> $ 13,000 <br /> $ 211,954 <br /> $ 4,983 <br /> $ 4,983 <br /> $ 4,210 <br /> $ 9,500 <br /> $ 4,440 <br /> $ 2,475 <br /> $ 13,060 <br /> $ 10,600 <br /> $ 850 <br /> $ 1,020 <br /> $ 904 <br /> $ 10,960 <br /> $ 4,080 <br /> $ 5,640 <br /> $ 8,880 <br /> $ 3,060 <br /> $ 1,020 <br /> $ 1,388 <br /> $ 15,440 <br /> $ 1,035 <br /> $ 765 <br /> Key <br /> $ 268 <br /> $ 4,790 <br /> $ 9,620 <br /> $ 3,350 <br /> $ 6,780 <br /> $ 3,495 <br /> $ 3,140 <br /> $ 11,400 <br /> $ 2,895 <br /> $ 5,160 <br /> $ 2,515 <br /> $ 520 <br /> $ 870 <br /> $ 255 <br /> $ 1,415 <br />ORANGE COUNTY, NC PAY SCHEDULE <br /> $ 4,470 <br /> $ 4,395 <br /> $ 10,080 <br /> $ 1,885 <br />DocuSign Envelope ID: 3C4C0744-8A68-4BE3-8967-7FABC6CFA5A1