<br />		Appropriated for this project:
<br />    												Current	FY 2022-23     FY 2022-23
<br /> 												FY 2022-23     Amendment       Revised
<br /> 		Project Expenditures       						$73,611,557      $182,600     $73,794,157
<br />    									Total Costs      $73,611,557      $182,600     $73,794,157
<br />    					Roofing Projects - CHCCS ($447,712) - Project# 54012
<br />		Revenues for this project:
<br />    												Current	FY 2022-23     FY 2022-23
<br /> 												FY 2022-23     Amendment       Revised
<br />		Bond Proceeds    									$0      $447,712 	$447,712
<br />		Qualified School Capital Bonds     					$4,630,000       	$0       $4,630,000
<br />		Transfer from General Fund 						$1,520,053       	$0       $1,520,053
<br />		Alternative Financing    							$691,676       	$0 	$691,676
<br />       							Total Project Funding	$6,841,729      $447,712       $7,289,441
<br />		Appropriated for this project:
<br />    												Current	FY 2022-23     FY 2022-23
<br /> 												FY 2022-23     Amendment       Revised
<br /> 		Project Expenditures 							$6,841,729      $447,712       $7,289,441
<br />    									Total Costs	$6,841,729      $447,712       $7,289,441
<br />  				Mechanical Systems 2016 Bonds - OCS ($418,635) - Project# 51038
<br />		Revenues for this project:
<br />    												Current	FY 2022-23     FY 2022-23
<br /> 												FY 2022-23     Amendment       Revised
<br />		Bond Proceeds       							$22,173,971       $418,635     $22,592,606
<br />		2/3rds Net Debt Bonds   							$50,000       	$0   	$50,000
<br />		Transfer from General Fund 						$1,118,185       	$0       $1,118,185
<br />		Lottery Proceeds  								$75,218       	$0   	$75,218
<br />       							Total Project Funding      $23,417,374      $418,635     $23,836,009
<br />		Appropriated for this project:
<br />    												Current	FY 2022-23     FY 2022-23
<br /> 												FY 2022-23     Amendment       Revised
<br /> 		Project Expenditures       						$23,417,374      $418,635     $23,836,009
<br />    									Total Costs      $23,417,374      $418,635     $23,836,009
<br />   		21.At the  May 2,  2023  Board  of County Commissioners'  Business  meeting,  the  County
<br />			authorized the draw of Lottery proceeds to fund capital projects for both school districts.
<br />			This amendment recognizes the increase of $1,402,354 to the General Fund in receiving
<br />			these state funds. The County uses these funds to pay down school related debt, and
<br />			provides additional pay-as-you-go funding for current capital projects.
<br />			SOCIAL JUSTICE IMPACT: There are no Orange County Social Justice Goals applicable
<br />			to this item.