4
<br /> Appropriated for this project:
<br /> Current FY 2022-23 FY 2022-23
<br /> FY 2022-23 Amendment Revised
<br /> School Capital Expenditures $2,075,602 ($538,145) $1,537,457
<br /> Total Costs $2,075,602 ($538,145) $1,537,457
<br /> Roof& Canopies Projects ($538,145) - Project#51026
<br /> Revenues for this project:
<br /> Current FY 2022-23 FY 2022-23
<br /> FY 2022-23 Amendment Revised
<br /> Alternative Financing $269,691 $0 $269,691
<br /> 2/3rds Net Debt Bonds $30,000 $0 $30,000
<br /> From General Fund $275,657 $538,145 $813,802
<br /> Total Project Funding $575,348 $538,145 $1,113,493
<br /> Appropriated for this project:
<br /> Current FY 2022-23 FY 2022-23
<br /> FY 2022-23 Amendment Revised
<br /> School Capital Expenditures $575,348 $538,145 $1,113,493
<br /> Total Costs $575,348 $538,145 $1,113,493
<br /> Cedar Ridge Classroom & Planning (-$1,078,476) - Project#51041
<br /> Revenues for this project:
<br /> Current FY 2022-23 FY 2022-23
<br /> FY 2022-23 Amendment Revised
<br /> 2016 Bonds $14,500,000 ($1,078,476) $13,421,524
<br /> Total Project Funding $14,500,000 ($1,078,476) $13,421,524
<br /> Appropriated for this project:
<br /> Current FY 2022-23 FY 2022-23
<br /> FY 2022-23 Amendment Revised
<br /> School Capital Expenditures $14,500,000 ($1,078,476) $13,421,524
<br /> Total Costs $14,500,000 ($1,078,476) $13,421,524
<br /> Classroom Building 2016 Bonds ($1,078,476) - Project#51042
<br /> Revenues for this project:
<br /> Current FY 2022-23 FY 2022-23
<br /> FY 2022-23 Amendment Revised
<br /> 2016 Bonds $1,284,250 $1,078,476 $2,362,726
<br /> Total Project Funding $1,284,250 $1,078,476 $2,362,726
<br />
|