Possible Timetable* <br />Efland Cheeks Park, Phase 2 <br />November Map revisions com lete, Committee report completed <br />December 9 BOCC receives Committee Report, provides feedback <br />.January- <br />February, 2004 BOCC discussion /approval of Phase 2 plan, (approve Phase 2 plan, <br />authorize staff to submit site plan, develop construction drawings and <br />bid documents, and solicit bids) <br />February, 2004 Site Plan re aced <br />February, 2004 Site Plan submitted to Planning <br />March, 2004 Site Plan approved (courtesy copy to Committee) <br />March-A ril Final construction drawings and bid documents re aced <br />Late-April Review of bid documents <br />May 3 Bids solicited <br />May 25 Bids due <br />May 28 Bid o ening <br />June 8 BOCC approves contract award <br />Tuly-October Construction (mechanism for communication with community <br />citizens in place) <br />Late-Fall, 2004 Phase 2 Completed <br />* -This timetable assumes best-case scenario, without unforeseen delays. <br />