Orange County NC Website
DSS Skills Development Center Smith Sinnett / 2020045 <br />Chapel Hill, North Carolina Orange County <br /> <br />CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 7 <br />plus items recently delivered. Include with list a statement of progress on and delivery dates for materials <br />or items of equipment fabricated or stored away from Project site. <br />C. Field Condition Reports: Immediately on discovery of a difference between field conditions and the <br />Contract Documents, prepare and submit a detailed report. Submit with a request for interpretation. <br />Include a detailed description of the differing conditions, together with recommendations for changing <br />the Contract Documents. <br />2.7 SPECIAL REPORTS <br />A. General: Submit special reports directly to Owner within one day(s) of an occurrence. Distribute copies <br />of report to parties affected by the occurrence. <br />B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, <br />whether or not related directly to the Work, prepare and submit a special report. List chain of events, <br />persons participating, response by Contractor's personnel, evaluation of results or effects, and similar <br />pertinent information. Advise Owner in advance when these events are known or predictable. <br />PART 3 - EXECUTION <br />3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE <br />A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual <br />construction progress and activities. Issue schedule one week before each regularly scheduled progress <br />meeting. <br />1. Revise schedule immediately after each meeting or other activity where revisions have been <br />recognized or made. Issue updated schedule concurrently with the report of each such meeting. <br />2. Include a report with updated schedule that indicates every change, including, but not limited to, <br />changes in logic, durations, actual starts and finishes, and activity durations. <br />3. As the Work progresses, indicate Actual Completion percentage for each activity. <br />B. Distribution: Distribute copies of approved schedule to Architect Owner, separate contractors, testing <br />and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule <br />responsibility. <br />1. Post copies in Project meeting rooms and temporary field offices. <br />2. When revisions are made, distribute updated schedules to the same parties and post in the same <br />locations. Delete parties from distribution when they have completed their assigned portion of the <br />Work and are no longer involved in performance of construction activities. <br />END OF SECTION 01 32 00 <br /> <br /> <br /> <br /> <br />DocuSign Envelope ID: ECCAC5A0-6CC8-4B37-8AD3-89D69F0AE1AE