Orange County NC Website
DSS Skills Development Center Smith Sinnett / 2020045 <br />Chapel Hill, North Carolina Orange County <br /> <br />CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 3 <br />1. Review software limitations and content and format for reports. <br />2. Verify availability of qualified personnel needed to develop and update schedule. <br />3. Discuss constraints, including phasing, work stages, area separations, and interim milestones. <br />4. Review schedule for work of Owner's separate contracts. <br />5. Review time required for review of submittals and resubmittals. <br />6. Review requirements for tests and inspections by independent testing and inspecting agencies. <br />7. Review and finalize list of construction activities to be included in schedule. <br />8. Review submittal requirements and procedures. <br />9. Review procedures for updating schedule. <br />1.6 COORDINATION <br />A. Coordinate preparation and processing of schedules and reports with performance of construction <br />activities and with scheduling and reporting of separate contractors. <br />B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, <br />Submittals Schedule, progress reports, payment requests, and other required schedules and reports. <br />1. Secure time commitments for performing critical elements of the Work from parties involved. <br />2. Coordinate each construction activity in the network with other activities and schedule them in <br />proper sequence. <br />PART 2 - PRODUCTS <br />2.1 SUBMITTALS SCHEDULE <br />A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by <br />construction schedule. Include time required for review, resubmittal, ordering, manufacturing, <br />fabrication, and delivery when establishing dates. <br />1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's <br />Construction Schedule. <br />2. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals <br />required during the first 60 days of construction. List those required to maintain orderly progress <br />of the Work and those required early because of long lead time for manufacture or fabrication. <br />a. At Contractor's option, show submittals on the Preliminary Construction Schedule, instead <br />of tabulating them separately. <br />3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's <br />Construction Schedule. <br />2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL <br />A. Procedures: Comply with procedures contained in AGC's "Construction Planning & Scheduling." <br />B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final <br />Completion. <br />1. Contract completion date shall not be changed by submission of a schedule that shows an early <br />completion date, unless specifically authorized by Change Order. <br />C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of <br />the Work. Comply with the following: <br />1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically <br />allowed by Architect. <br />2. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section <br />"Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's <br />Construction Schedule with Submittals Schedule. <br />DocuSign Envelope ID: ECCAC5A0-6CC8-4B37-8AD3-89D69F0AE1AE