Orange County Facility Renovations <br />Hillsborough, NC <br />Smith Sinnett CONSTRUCTION PROGRESS DOCUMENTATION <br />2020046/2020047/2020048/2020049/2020055 01 32 00 - 5 <br />B. Preliminary Network Diagram: Submit diagram within 14 days of date established for the Notice to <br />Proceed. Outline significant construction activities for the first 60 days of construction. Include skeleton <br />diagram for the remainder of the Work and a cash requirement prediction based on indicated activities. <br />C. CPM Schedule: Prepare Contractor's Construction Schedule using a computerized, time-scaled CPM <br />network analysis diagram for the Work. <br />1. Develop network diagram in sufficient time to submit CPM schedule so it can be accepted for use <br />no later than 30 days after date established for the Notice to Proceed. <br />a. Failure to include any work item required for performance of this Contract shall not excuse <br />Contractor from completing all work within applicable completion dates, regardless of <br />Architect's approval of the schedule. <br />2. Conduct educational workshops to train and inform key Project personnel, including <br />subcontractors' personnel, in proper methods of providing data and using CPM schedule <br />information. <br />3. Establish procedures for monitoring and updating CPM schedule and for reporting progress. <br />Coordinate procedures with progress meeting and payment request dates. <br />4. Use "one workday" as the unit of time. Include list of nonworking days and holidays incorporated <br />into the schedule. <br />D. CPM Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the <br />preliminary network diagram, prepare a skeleton network to identify probable critical paths. <br />1. Activities: Indicate the estimated time duration, sequence requirements, and relationship of each <br />activity in relation to other activities. Include estimated time frames for the following activities: <br />a. Preparation and processing of submittals. <br />b. Mobilization and demobilization. <br />c. Purchase of materials. <br />d. Delivery. <br />e. Fabrication. <br />f. Utility interruptions. <br />g. Installation. <br />h. Work by Owner that may affect or be affected by Contractor's activities. <br />i. Testing. <br />2. Critical Path Activities: Identify critical path activities, including those for interim completion <br />dates. Scheduled start and completion dates shall be consistent with Contract milestone dates. <br />3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. <br />Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the <br />CPM schedule within the limitations of the Contract Time. <br />4. Format: Mark the critical path. Locate the critical path near center of network; locate paths with <br />most float near the edges. <br />a. Subnetworks on separate sheets are permissible for activities clearly off the critical path. <br />E. Initial Issue of Schedule: Prepare initial network diagram from a list of straight "early start-total float" <br />sort. Identify critical activities. Prepare tabulated reports showing the following: <br />1. Contractor or subcontractor and the Work or activity. <br />2. Description of activity. <br />3. Principal events of activity. <br />4. Immediately preceding and succeeding activities. <br />5. Early and late start dates. <br />6. Early and late finish dates. <br />7. Activity duration in workdays. <br />8. Total float or slack time. <br />9. Average size of workforce. <br />10. Dollar value of activity (coordinated with the Schedule of Values). <br />F. Schedule Updating: Concurrent with making revisions to schedule, prepare tabulated reports showing the <br />following: <br />1. Identification of activities that have changed. <br />2. Changes in early and late start dates. <br />3. Changes in early and late finish dates. <br />4. Changes in activity durations in workdays. <br />5. Changes in the critical path. <br />6. Changes in total float or slack time. <br />DocuSign Envelope ID: 09980A3B-0691-41B4-854D-3865F2287392