Orange County Facility Renovations <br />Hillsborough, NC <br />Smith Sinnett CONSTRUCTION PROGRESS DOCUMENTATION <br />2020046/2020047/2020048/2020049/2020055 01 32 00 - 3 <br />B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, <br />Submittals Schedule, progress reports, payment requests, and other required schedules and reports. <br />1. Secure time commitments for performing critical elements of the Work from parties involved. <br />2. Coordinate each construction activity in the network with other activities and schedule them in <br />proper sequence. <br />PART 2 - PRODUCTS <br />2.1 SUBMITTALS SCHEDULE <br />A. Preparation: Submit a schedule of submittals, arranged in chronological order by dates required by <br />construction schedule. Include time required for review, resubmittal, ordering, manufacturing, <br />fabrication, and delivery when establishing dates. <br />1. Coordinate Submittals Schedule with list of subcontracts, the Schedule of Values, and Contractor's <br />Construction Schedule. <br />2. Initial Submittal: Submit concurrently with preliminary bar-chart schedule. Include submittals <br />required during the first 60 days of construction. List those required to maintain orderly progress <br />of the Work and those required early because of long lead time for manufacture or fabrication. <br />a. At Contractor's option, show submittals on the Preliminary Construction Schedule, instead <br />of tabulating them separately. <br />3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's <br />Construction Schedule. <br />2.2 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL <br />A. Procedures: Comply with procedures contained in AGC's "Construction Planning & Scheduling." <br />B. Time Frame: Extend schedule from date established for the Notice to Proceed to date of Final <br />Completion. <br />1. Contract completion date shall not be changed by submission of a schedule that shows an early <br />completion date, unless specifically authorized by Change Order. <br />C. Activities: Treat each story or separate area as a separate numbered activity for each principal element of <br />the Work. Comply with the following: <br />1. Activity Duration: Define activities so no activity is longer than 20 days, unless specifically <br />allowed by Architect. <br />2. Submittal Review Time: Include review and resubmittal times indicated in Division 01 Section <br />"Submittal Procedures" in schedule. Coordinate submittal review times in Contractor's <br />Construction Schedule with Submittals Schedule. <br />3. Substantial Completion: Indicate completion in advance of date established for Substantial <br />Completion, and allow time for Architect's administrative procedures necessary for certification of <br />Substantial Completion. <br />D. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as <br />follows in schedule, and show how the sequence of the Work is affected. <br />1. Phasing: Arrange list of activities on schedule by phase. <br />2. Work under More Than One Contract: Include a separate activity for each contract. <br />3. Work by Owner: Include a separate activity for each portion of the Work performed by Owner. <br />4. Work Restrictions: Show the effect of the following items on the schedule: <br />a. Coordination with existing construction. <br />b. Limitations of continued occupancies. <br />c. Use of premises restrictions. <br />d. Provisions for future construction. <br />e. Seasonal variations. <br />f. Environmental control. <br />5. Work Stages: Indicate important stages of construction for each major portion of the Work, <br />including, but not limited to, the following: <br />DocuSign Envelope ID: 09980A3B-0691-41B4-854D-3865F2287392