<br /> NCDOT DIV 7 PROJECTS LOCATED IN TARPO-UNDER DEVELOPMENT
<br /> TIPIWBS# Description Let/Start Date Completion Cost Status Project Lead Comments/PE Suspended in May 2020
<br /> Date
<br /> SS-4907CD Horizontal curve improvements on SR 1710(Old NC 10)west of Jun.2022 Nov.2022 $261,000 Planning and design activities underway Chad Reimakoski DMP,State Spot Safety,DPOC,Surveys complete,$40,000 PE,65%plans pending,
<br /> 47936.1.1 SR 1561/SR 1709(Lawrence Road)east of Hillsborough. ROW plans complete June/July,SCR moved ROW to 9/30/19 and Let from 12/5119 to
<br /> 47936.2.1 Improvements consist of wedging pavement and grading 4/3120,SCR moved ROW to 11/27/19 and let 6/1/20,SCR moved ROW to 11/25/20 and
<br /> 47936.3.1 shoulders. Let 6/1/21 by CE directive(1 year push),No public meeting scheduled,Finish design In-
<br /> house,PE continue working on 65%plans,SCR moved ROW to 11/24/21 and LET to
<br /> 6/1/22,HB77 Candidate,SS Move Forward List 11/23/20
<br /> SS-6007E All Way Stop installation and flashing beacon revisions at the Jun.2022 Oct.2022 $28,800 PE funds approved 3/5/20 and released Dawn McPherson DMP,State Spot Safety,OCC,PE$2,700,HB77 Candidate,SS Move Forward List
<br /> 49115.1.1 intersection of SR 1005(Old Greensboro Road)and SR 1956 6/23/20 11/23/20
<br /> 49115.3.1 (Crawford Dairy Road/Orange Chapel Clover Garden Road).
<br /> 1-5958 Pavement rehabilitation on 1-40/1-85 from west of SR 1114 11/17/26 FY 2028 $8,690,000 Planning activities pending Chris Smitherman DMP,STIP,DDRL,Executive Hold,Revised STIP 2020-2029 Let 11/17/26,SCR to
<br /> 45910.1.1 (Buckhom Road)to west of SR 1006(Orange Grove Road). move LET from 11/21123 to 11117/26 to assist in balancing funds
<br /> 45910.3.1
<br /> 1-5959 Pavement rehabilitation on 1-85 from west of SR 1006(Orange 11/16/27 FY2029 $11,156,000 Planning activities pending Chris Smitherman DMP,STIP,DDRL,Executive Hold,Revised STIP 2020-2029 Let 11/16/27,SCR to
<br /> 45911.1.1 Grove Road)to Durham County line. move LET from 11/19/24 to 11/16/27 to assist in balancing funds
<br /> 45911.3.1
<br /> R-5821A Construct operational improvements including 6120128 FY2030 $3,194,000 Planning and design activities underway, Chris Smitherman DMP,STIP,DDRL,Waiting on feasibility corridor study from DCHCMPO,NTP 1/23/18,
<br /> 47093.1.2 Bicycle/Pedestrian accommodations on NC 54 from SR 1006 coordinating with NC54 West Corridor Study seeping meeting 6/25/18,ROW acquisition scheduled 6/15/20($730,000),Executive
<br /> 47093.2.2 (Orange Grove Road)to SR 1107/SR 1937(Old Fayetteville Hold,SCR move ROW to 6/15/21 due to insufficient funds,Revised STIP 2020-2029 Let
<br /> 47093.3.2 Road). 6/20/28,SCR move ROW from 6/15/21 to 5/15/26 and LET from 6/21122 to 6/20/28
<br /> for balancing funds,CON Build NC Bonds
<br /> Page 1 TARPO-Orange Co Apr.2021