DocuSign Envelope ID:27028AA0-327E-4DEF-B3D5-A4F12D5863EC <br /> • Structures: Detention Facility and POB—will need approximately 3-4 more weeks (est.—130 hours) here for steel <br /> joists, miscellaneous masonry and concrete, and structural steel for POB. Structures will be at Special Inspector <br /> rate ($75)to complete Special Inspections. <br /> • Sitework& Paving:total for remaining sitework, hardscapes, roadway subgrade, roadway abc stone, concrete <br /> paving and asphalt paving. Based off of our understanding from Bordeaux's schedule,this will be approximately <br /> 4 weeks (est. —160 hours) of onsite time to wrap up sitework inspections and testing. Once we get into this last <br /> phase of work, Summit will utilize the Field Technician 2 rate ($60)to complete sitework& paving. <br /> Given what is left,we feel we have a good grasp on what is remaining and can manage to these requested additional <br /> hours. Will need to finish the project strong and help deliver the best possible end product for the County. Let me know <br /> if you have any questions. <br /> Take care, <br /> -Jeff <br /> Jeff Elliott, PE <br /> Geotech & CMT/SI Manager <br /> Tel: 919-732-3883 x3130 <br /> Fax:919-732-6676 <br /> Cell:919-796-0799 <br /> USUI�*lt#11T <br /> DESIGN AND ENGINEERING SERVICES <br /> ®M©® <br /> From: Don Dewey, PE<don.dewey@summitde.net> <br /> Sent: Monday, October 5, 2020 10:01 AM <br /> To:Jeff Elliott, PE<jeff.elliott@summitde.net> <br /> Cc:Angel Barnes<abarnes@orangecountync.gov> <br /> Subject: FW: CMT/SI Detention Center <br /> Jeff, <br /> Can you provide Angel with a rundown of what testing is left out at Northern Campus/Detention Center and how/if that <br /> effects our budget. <br /> Thanks. <br /> Don Dewey, PE <br /> Senior Geotechnical Engineer <br /> Tel: 919-732-3883 x3108 <br /> Fax:919-732-6676 <br /> 0SUt*#11T <br /> DESIGN AND ENGINEERING SERVICES <br /> 119J©R <br /> 2 <br />