12 <br /> Additional Scope of Remediation post <br /> Investigative Demolition #2 <br /> ADDED SCOPE <br /> REMOVE ALL BRICK AND CAST STONE TO INSTALL A CONTINUOUS DRAINAGE PLANE <br /> REMOVE ALL DRYWALL, REPLACE MECHANICAL SYSTEM, REPAIR RATED WALL BREACHES <br /> REASONING <br /> UPON INVESTIGATIVE DEMOLITION #2, MORE BREECHES IN SHEATHING WERE FOUND; MORE AREAS OF <br /> WATER INFILTRATION WERE FOUND AND IT IS NO LONGER FEASIBLE TO REMEDIATE WITHOUT ADDED <br /> SCOPE (NOTE: UNDER THE CURRENT SCOPE THIS WOULD HAVE BEEN REVEALED DURING <br /> CONSTRUCTION RESULTING IN A SIGNIFICANT CHANGE ORDER) <br /> ORIGINAL DESIGN AND CONSTRUCTION FUNDEMENTALLY IS FLAWED IN KEEPING WATER OUT OF THE <br /> BUILDING <br /> • RESULTS <br /> • MAINTENANCE IS CRITICAL TO ENSURE CAST STONE SEALANT IS INTACT <br /> • NO ABILITY TO PROVIDE A COMPLETE SECONDARY LAYER OF SAFETY INSIDE WALL CAVITY <br /> • ADDITIONAL COSTS: $2M+ <br /> ■ <br />