Orange County NC Website
5thWall Building Diagnostics Consultants Government Services Annex <br /> District Attorney Office <br /> Roof Replacement <br /> November 2009 <br /> 1904 Schedule <br /> A . Within seven days after receipt of Notice to Proceed the Contractor shall submit one <br /> reproducible and two prints of the construction schedule to the Designer . These documents <br /> shall be forwarded to the Designer via a carrier that will guarantee delivery on the next <br /> working day. <br /> Be On the first working day of each month the schedule shall be updated and two prints <br /> submitted to the Owner . <br /> PART 2 PRODUCTS <br /> 2 . 01 Diagram <br /> A. Graphically show the sequence and interdependence of all activities necessary to complete <br /> the Work and the order in which such activities are to be accomplished as planned by the <br /> Contractor and its project field supervisor in coordination with all subcontractors whose <br /> work is shown on the diagram . Activities shown on the diagram shall include, but are not <br /> necessarily limited to : <br /> 1 . Submittals and approvals of shop drawings and samples <br /> 2 . Procurement of equipment and materials <br /> 3 . Project mobilization <br /> 4 . Demolition/Preparation <br /> 5 . Construction <br /> 6 . Miscellaneous Work <br /> 7 . Final clean up <br /> 8 . Final inspection <br /> 9 . All activities by the Owner which affect progress, required completion dates , or <br /> both, for all and each part of the work. <br /> Be The detail of information shall be such that duration times of activities shall normally range <br /> from one to thirty days . The selection and number of activities shall be subject to approval <br /> by the Owner. <br /> Co Mathematical Analysis : Tabulate each activity of detailed network diagrams , using <br /> calendar dates , and identify for each activity. <br /> 1 . Preceding and following event numbers <br /> 2 . Activity description <br /> 3 . Estimated duration of activity, in maximum 30 day intervals <br /> 4 . Earliest start date <br /> 5 . Earliest finish date <br /> 6 . Actual start date <br /> 7 . Actual finish date <br /> 8 . Latest start date <br /> 9 . Latest finish date <br /> 10 . Total and free floats accrue float time to Owner and to Owner 's benefit <br /> 11 . Monetary value of activity, keyed to Schedule of Values <br /> 12 . Percentage of activity completed <br /> 13 . Responsibility <br /> 09 -26 Construction Progress Schedule <br /> 01321602 <br />