Eubanks Road Waste & Recycling Facilities <br />Project Category:Solid Waste Capital Project Status:Active Project Type <br />Functional Service <br />Area:Community Services <br />Proposed Bid <br />Award Date:1/24/17 New <br />Department:Solid Waste Starting Date:3/6/17 Expansion <br />Project Number:Fund 50 Completion Date:3/23/2018 Renovation X <br />Replacement <br />Project Description/Justification:Solid Waste Facilities Improvements – (Eubanks Road Waste and Recycling Center) <br />($1,775,535 remaining from original 3 million debt financing; $303,311 remaining from <br />completed and under budget landfill closure project). This project includes a <br />modernization of the existing center, and the relocation of the main landfill entrance and <br />scale house from the south side of Eubanks Road to the north side of Eubanks Road; <br />($3,145,858); ($30,000)grant (reimbursable) for Compactor. <br />Initial bids (Feb. 2, 2016) exceeded the project budget and deduct alternates and <br />negotiations with the contractor were unsuccessful in bringing the project in under <br />budget. The site was redesigned in an effort to reduce costs and was rebid. The new <br />low bid was negotiated and value engineered to $3,100,000, not including stationary <br />compactors that were planned to be bid separately. Stationary compactors ($214,000) will be purchased from the separate <br />Sanitation – Vehicle/Equipment Replacement project. Prior year’s operating budget includes $44,000 for establishment of a <br />temporary center used during construction and associated public education & outreach. <br />Current year operating costs include three months of two new 30/hr./wk. part-time, permanent center operators and <br />installation of security cameras. Year one operating costs include electricity, and increased operating hours for the HHW <br />facility, and recurring capital for future replacement of 8 receiver boxes for containing and hauling compacted materials, and <br />8 stationary compactor units. Additional budgetary savings of $93,552 was realized in FY 2016-17 due to the installation of <br />compactors. <br />FINANCIAL SUMMARY <br />Current Year 1 Year 2 Year 3 Year 4 Year 5 Five Year 6 <br />Prior Years Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Fiscal Year Year to <br />Project Budget Funding 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 Total Year 10 <br />Expenses <br /> Land/Building - <br /> Professional Services - <br /> Construction/Repairs/Renovations 3,145,858 - <br /> Equipment/Furnishings - <br /> Total Project Budget:3,145,858-------- <br />Funding Sources <br /> Solid Waste Funds 303,311 - <br /> Debt Financing 2,842,547 - <br /> Grant Funds - <br /> Total 3,145,858-------- <br />Impact on Solid Waste Fund Operating Budget <br /> Personnel Services 110,909 72,194 72,916 73,645 74,382 74,382 74,382 369,707 383,220 <br /> Operations 109,013 47,200 48,144 49,106 50,090 50,090 50,090 247,520 271,196 <br /> Recurring Capital 66,855 35,500 35,500 35,500 35,500 35,500 35,500 177,500 177,500 <br /> New/Addl Revenue - <br /> Total Operating Costs 286,777 154,894 156,560 158,251 159,972 159,972 159,972 794,727 831,916 <br />193