ORANGE COUNTY SCHOOLS
<br /> FY2020 UNFUNDED MAJOR PROJECTS
<br /> SCOPE OF WORK LOCATION PROJECTED COST
<br /> CENTRAL OFFICE ADDITION(PRICE INCLUDES TOTAL PROJECT COSTS) B E $4,688,000
<br /> RENOVATE EXISTING K-1 WING(PRICE INCLUDES TOTAL PROJECT COSTS) CAMERON PARK 2,030,400
<br /> RENOVATE EXISTING OFFICE SUITE(PRICE INCLUDES TOTAL PROJECT COSTS) CAMERON PARK 265,000
<br /> RENOVATE/EXPAND EXISTING 2-4 WING(PRICE INCLUDES TOTAL PROJECT COSTS) CAMERON PARK 3,784,000
<br /> DECONSTRUCT/RECONSTRUCT4-5 WING(PRICE INCLUDESTOTAL PROJECTCOSTS) CAMERON PARK 5,500,000
<br /> NEW CONNECTOR(PRICE INCLUDES TOTAL PROJECT COSTS) CAMERON P 484,375
<br /> FIELD HOUSE(PRICE INCLUDES TOTAL PROJECT COSTS) CEDAR R 2,400,000
<br /> CARPET REPLACEMENT MEDIA CENTER CEDAR RIDGE $90,000
<br /> BOILER REPLACEMENT CEDAR RIDGE $75,000
<br /> OFFICE EXPANSION(PRICE INCLUDES TOTAL PROJECT COSTS) CENIRALELEM $414,000
<br /> RENOVATE MAIN ENTRANCE(PRICE INCLUDES TOTAL PROJECT COSTS) CW STANFORD700,000
<br /> REPLACE OUTDOOR STORAGE BUILDING CW STANFORD $45,000
<br /> MEDIA CENTER RENOVATIONS CW STANFORD $200,000
<br /> PAVING ASSESSMENT FY 19 CW STANFORD $352,600
<br /> NON-PROTOTYPICAL ELEMENTARY SCHOOL#8 DISTRICT 28,500,000
<br /> FURNITURE UPGRADES(YEAR 1 OF 5) DISTRICT $250,000
<br /> PRE-K ADDITION(PRICE INCLUDES TOTAL PROJECT COSTS) EFLAND 690,000
<br /> CLASSROOM EXPANSION(PRICE INCLUDES TOTAL PROJECT COSTS) EFLAND CHEEK GLOBAL1,968,750
<br /> MAIN ENTRANCE ADDITION(PRICE INCLUDES TOTAL PROJECT COSTS) GRADY BROWN $897,000
<br /> MEDIA CENTER/TEACHER SUPPORT RENOVATION(PRICE INCLUDES TOTAL PROJECT COST' GRADY GRAD BROWN $1,950,000
<br /> BMP Ponds District Wide $150,000
<br /> WATER HEATER KITCHEN GRAVELLY HILL $75,000
<br /> REPLACE BUILDING 100 ONLY(PRICE INCLUDES TOTAL PROJECT COSTS) ELEMENTARY $14,422,000
<br /> BUILDING CONNECTORS(PRICE INCLUDES TOTAL PROJECT COSTS) ELEMENTARY $1,468,750
<br /> LEARNING CENTER FLOORING ELEMENTARY $30,000
<br /> PAVING ASSESSMENT FY 19 ELEMENTARY $82,700
<br /> REPLACE MAINTENANCE COMPLEX(TOTAL PROJECT COSTS) M 4,688,000
<br /> ADD MAINTENANCE STORAGE(TOTAL PROJECT COSTS) MAINTENANCE 2,265,700
<br /> WINDOW/DOOR REPLACEMENTS MAINTENANCE $40,000
<br /> DRAINAGE PROJECT NEW HOPE $90,000
<br /> REPLACE WORKFORCE DEVELOPMENT BUILDING(PRICE INCLUDES TOTAL PROJECT COSTS 3,625,000
<br /> VCTASBESTOSTILE REPLACEMENT OHS $250,000
<br /> PAVING ASSESSMENT FY19 OHS $439,900
<br /> PAVING ASSESSMENT IMMEDIATE TRANSPORTATION $312,800
<br /> $83,223,975
<br /> FY20-UNFUNDED MAJOR PROJECTS--Page 1 of 1
<br /> 172
<br />
|