DocuSign Envelope ID: B94F2D40-3B3C-47A7-86C2-6F1 B4F92C62C <br /> SECTION 01 32 00-CONSTRUCTION PROGRESS DOCUMENTATION <br /> 10. Emergency procedures. <br /> 11. Orders and requests of authorities having jurisdiction. <br /> 12. Change Orders received and implemented. <br /> 13. Construction Change Directives received. <br /> 14. Services connected and disconnected. <br /> 15. Equipment or system tests and startups. <br /> 16. Partial Completions and occupancies. <br /> 17. Substantial Completions authorized. <br /> B. Field Condition Reports: Immediately on discovery of a difference between field conditions and the Contract <br /> Documents, prepare a detailed report. Submit in electronic format with a Request for Interpretation. Include a <br /> detailed description of the differing conditions, together with recommendations for changing the Contract <br /> Documents. <br /> 2.5 SPECIAL REPORTS <br /> A. General: Submit special reports in electronic format directly to Owner within one day of an occurrence. Distribute <br /> copies of report to parties affected by the occurrence. <br /> PART 3 -EXECUTION <br /> 3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE <br /> A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction <br /> progress and activities. Issue schedule one week before each regularly scheduled progress meeting. <br /> 1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or <br /> made. Issue updated schedule concurrently with the report of each such meeting. <br /> 2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in <br /> logic, durations, actual starts and finishes, and activity durations. <br /> 3. As the Work progresses, indicate Actual Completion percentage for each activity. <br /> B. Distribution: Distribute copies of approved schedule to Architect, Owner, separate contractors, testing and <br /> inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility. <br /> 1. Post copies in Project meeting rooms and temporary field offices. <br /> 2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. <br /> Delete parties from distribution when they have completed their assigned portion of the Work and are no <br /> longer involved in performance of construction activities. <br /> END OF SECTION 01 32 00 <br /> ©BOOMERANG DESIGN#1835 01 32 00-4 510 Meadowlands Drive,Hillsborough, NC <br /> ORANGE COUNTY,NC 12/07/2018 <br />