| 2
<br />   		•    rebuilding the exterior office and building space walls,
<br />   		•    removing and reworking all electrical components,
<br />   		•    cleaning existing heating and cooling system located throughout the building, including
<br />			the all exterior and interior HVAC units, and replacing select units for humidity control.
<br />   		•    replacing all contaminated flooring and ceiling tiles,
<br />   		•    repair the existing roof system, including equipment curbs and parapet walls,
<br />   		•    reattaching the gutter system,
<br />   		•    obtaining all necessary permits and other documentation necessary to complete the full
<br />			remediation and reconstruction as called out in the scope of work.
<br />   		•    Removal of all emergency services communication equipment and reinstallation
<br />   		•    temporary off site facility for administrative staff
<br />   		•    temporary on site facility for Logistics' staff
<br />      	Since this project was not anticipated as part of the Capital Budget, a budget amendment is also
<br />      	necessary to finance this project.  Staff recommends that the following funds totaling $632,250
<br />      	be reallocated from existing projects, as well as approving new financing of $1,846,209 needed
<br />      	to fund  the  total  costs  of $2,478,459,  including  contingency funds,  for the  remediation  and
<br />      	reconstruction of the Emergency Services building.   This budget amendment provides for the
<br />      	reallocation of funds and amends the following Capital Project Ordinances:
<br />      			HVAC Projects (-$105,000) - Project#30018
<br />      			Revenues for this project:
<br /> 										Current  	FY 2018-19       FY 2018-19
<br />       									FY 2018-19       Amendment 	Revised
<br />				Alternative Financing      		$2,303,200	($105,000)       $2,198,200
<br />				From General Fund   			$669,723   		$0  	$669,723
<br />   					Total Project Funding	$2,972,923	($105,000)       $2,867,923
<br />     			Appropriated for this project:
<br /> 										Current  	FY 2018-19       FY 2018-19
<br />       									FY 2018-19       Amendment 	Revised
<br />				HVAC Projects      			$2,972,923	($105,000)       $2,867,923
<br /> 							Total Costs	$2,972,923	($105,000)       $2,867,923
<br />      			Parking Lot Repairs/Paving (-$16,000) - Project#30029
<br />      			Revenues for this project:
<br /> 										Current  	FY 2018-19       FY 2018-19
<br />       									FY 2018-19       Amendment 	Revised
<br />				Alternative Financing 			$120,000   		$0  	$120,000
<br />				From General Fund    			$16,000   	$16,000   		$0
<br />   					Total Project Funding   	$136,000  	($16,000)  	$120,000
<br />      			Appropriated for this project:
<br /> 										Current  	FY 2018-19       FY 2018-19
<br />       									FY 2018-19       Amendment 	Revised
<br />				Parking Lot Repairs Project 		$136,000  	($16,000)  	$120,000
<br /> 							Total Costs   	$136,000  	($16,000)  	$120,000
<br /> |