<br /> Change Proposal Form
<br /> Project: Efland SS to Mebane Phase 2
<br /> Contract: 16.01904
<br /> Contractor: JF Wilkerson Contracting,Inc.
<br /> Utility/
<br /> Construction Proposal No. 006
<br /> Project No. CIP 30044
<br /> Contractor No. C077
<br /> Description of Change:
<br /> Revised Line A, Plan Sheet 6 Adjust Depth per Owner Request.
<br /> Value Engineered Cost Determination for Adjusted Depth as shown
<br /> Item Unit Qty Bid Qty Revised Unit Price Bid Cost Revised Cost Difference
<br /> 12"PVC Gravity Sewer 6-8 Ft Depth LF 24 101 $ 49.00 $ 1,176.00 $ 4,949.00 $ 3,773.00
<br /> 12"PVC Gravity Sewer 8-10 Ft Depth LF 64 209 $ 56.00 $ 3,584.00 $ 11,704.00 $ 8,120.00
<br /> 12"PVC Gravity Sewer 10-12 Ft Depth LF 76 0 $ 59.00 $ 4,484.00 $ - $ (4,484.00)
<br /> 12"PVC Gravity Sewer 12-14 Ft Depth LF 88 0 $ 74.00 $ 6,512.00 $ $ (6,512.00)
<br /> 12"PVC Gravity Sewer 14-16 Ft Depth LF 121 0 $ 80.00 $ 9,680.00 $ $ (9,680.00)
<br /> 12"DIP Gravity Sewer 6-8 Ft Depth LF 0 15 $ 85.00 $ - $ 1,275.00 $ 1,275.00
<br /> 12"DIP Gravity Sewer 8-10 Ft Depth LF 0 35 $ 88.00 $ - $ 3,080.00 $ 3,080.00
<br /> 12"DIP Gravity Sewer 10-12 Ft Depth LF 6 90 $ 91.00 $ 546.00 $ 8,190.00 $ 7,644.00
<br /> 12"DIP Gravity Sewer 12-14 Ft Depth LF 25 70 $ 98.00 $ 2,450.00 $ 6,860.00 $ 4,410.00
<br /> 12"DIP Gravity Sewer 14-16 Ft Depth LF 40 75 $ 100.00 $ 4,000.00 $ 7,500.00 $ 3,500.00
<br /> 12"DIP Gravity Sewer 16-18 Ft Depth LF 62 285 $ 120.00 $ 7,440.00 $ 34,200.00 $ 26,760.00
<br /> 12"DIP Gravity Sewer 18-20 Ft Depth LF 131 52 $ 130.00 $ 17,030.00 $ 6,760.00 $ (10,270.00)
<br /> 12"DIP Gravity Sewer 20-22 Ft Depth LF 179 0 $ 150.00 $ 26,850.00 $ - $ (26,850.00)
<br /> 12"DIP Gravity Sewer 22-24 Ft Depth LF 60 0 $ 180.00 $ 10,800.00 $ - $ (10,800.00)
<br /> 4'Manhole 8-10 Ft EA 0 1 $ 4,600.00 $ - $ 4,600.00 $ 4,600.00
<br /> 4'Manhole 10-12 Ft EA 0 1 $ 5,000.00 $ - $ 5,000.00 $ 5,000.00
<br /> 5'Manhole 16-18 Ft EA 2 0 $ 7,800.00 $ 15,600.00 $ - $ (15,600.00)
<br /> 5'Manhole 20-22 Ft EA 0 1 $ 8,700.00 $ - $ 8,700.00 $ 8,700.00
<br /> 5'Manhole 24-26 Ft EA 1 0 $ 30,000.00 $ 10,000.00 $ - $ (10,000.00)
<br /> Directional Drill LF 56 60 $ 270.00 $ - $ 1,080.00 $ 1,080.00
<br /> Total Costs per Revised Plan Sheet 6 $ 120,152.00 $ 103,898.00 $ (16,254.00)
<br /> Time Extension Request 0 Days
<br /> The contractor agrees to perform the work outlined in thes change proposal for the amount specified above and in accordance with the
<br /> Contract documents if the work is authorized by the Owner.
<br /> Contractor Signature: Gicrmw Date
<br /> 12/14/2018
<br /> e. y
<br /> Approval Recommended by Engineer: �� �,,,,� Date
<br /> Date �8
<br /> Owner Representative: ��sci
<br /> 12/'-L4/'2 0 19
<br /> Approval Recommended: Date
<br /> CPR 006