22 <br /> Attachment D - Key Milestone Listing <br /> Estimated Schedule: <br /> Project Kick-Off/Data Gathering: Late Fall 2018 <br /> 30% SD Set: Spring 2019 <br /> 60% DD Set: Summer 2019 <br /> 100% Construction Documents: Fall 2019 <br /> Permitting: 3-6 months <br /> Bidding and Contracting: Fall 2019 <br /> Start Construction: Late Fall 2019 <br /> Project completed by: Spring/Summer 2020 <br /> 20 <br /> Revised 10/17 <br />