2
<br /> Chapel Hill — Carrboro City Schools ($217,000):
<br /> ADA Projects ($35,000) — Project # 54000 (Funds will be used for access improvements at
<br /> schools throughout the district).
<br /> Revenues for this project:
<br /> Current FY FY 2018-19 FY 2018-19
<br /> 2018-19 Amendment Revised
<br /> From General Fund PAYG $310,616 $35,000 $345,616
<br /> Total Project Funding $310,616 $35,000 $345,616
<br /> Appropriated for this project:
<br /> Current FY FY 2018-19 FY 2018-19
<br /> 2018-19 Amendment Revised
<br /> ADA Projects $310.616 $35,000 $345.616
<br /> Total Costs $310,616 $35,000 $345,616
<br /> Abatement Projects ($5,000) — Project # 54001 (Funds will be used to complete scheduled
<br /> abatement work).
<br /> Revenues for this project:
<br /> Current FY FY 2018-19 FY 2018-19
<br /> 2018-19 Amendment Revised
<br /> From General Fund PAYG $735,080 $5,000 $740,080
<br /> Total Project Funding $735,080 $5,000 $740,080
<br /> A ppropriated for this project:
<br /> Current FY FY 2018-19 FY 2018-19
<br /> 2018-19 Amendment Revised
<br /> Abatement Projects $735,080 $5,000 $740,080
<br /> Total Costs $735,080 $5,000 $740,080
<br /> Classroom/Building Improvements ($2,000) — Project # 53025 (Funds will be used to
<br /> complete the science classroom casework improvements at Phillips Middle School).
<br /> Revenues for this project:
<br /> Current FY FY 2018-19 FY 2018-19
<br /> 2018-19 Amendment Revised
<br /> From General Fund PAYG $1,523,607 $2,000 $1,525,607
<br /> 2/3 Net Debt Bonds $714,000 $0 $714,000
<br /> Alternative Financing $250,000 $0 $250,000
<br /> Total Project Funding $2,487,607 $2,000 $2,489,607
<br /> Appropriated for this project:
<br /> Current FY FY 2018-19 FY 2018-19
<br /> 2018-19 Amendment Revised
<br /> Classroom/Building Improvements $2,487,607 $2,000 $2,489,607
<br /> Total Costs $2,487,607 $2,000 $2,489,607
<br />
|