Orange County NC Website
CHANGE ORDER NO.: 4 <br />Page 1 of 4 <br />101: KIM" <br />CHANGE ORDER NO.: 4 DATE: September 5, 2018 <br />Project: Historic Rogers Road Sewer Expansion Project <br />Contractor: Moffat Pipe, Inc. <br />Engineer /Architect: URS Corporation — North Carolina <br />CONTRACTOR is directed to make the following changes in the Contract Documents. <br />Description: <br />Moffat Pipe, Inc. is requesting the following revisions to the substantial completion and final completion <br />dates of the contract to account for delays in the project considered to be no fault of their own and beyond <br />their control. Moffat Pipe, Inc. is requesting an additional 18 calendar days. The requested number of <br />additional contract days are as follows: 17 calendar days for weather delays experienced between March <br />235 2018 and August 20, 2018, and one (1) calendar day associated with the additional work for items <br />requested by OWASA on the May 25, 2018 punch list walkthrough. The requested number of delay days <br />does not account for potential future delays, or delays associated with other concerns not specifically <br />mentioned herein. <br />Moffat Pipe, Inc. is also requesting an additional $4,000.00 to compensate them for two items identified <br />and requested by OWASA on the May 25, 2018 punch list walkthrough, and additional staking due to <br />homeowners removing surveyors stakes on multiple occasions. A more detailed explanation of each of the <br />requested revisions to the Contract Price is below. <br />1) The two items identified on the punch list walkthrough that are not covered under the original <br />construction contract are the addition of rip rap along the second stream crossing and spring well <br />located on the Glenbrooke HOA property, and four (4) sewer valve covers for the tracer wire along <br />the PVC pipe in Outfall R. An additional day for this work has already been included in the itemized <br />list of delays listed seen in Attachment A. <br />2) Moffat Pipe was required to call out their subcontractor to re -stake easements approximately three <br />times in two different locations due to homeowners removing the stakes even though OWASA <br />communicated the need for the stakes and requested that homeowners not disturb them. <br />The following lines shall be added to Section 00 4144, Unit Price Contract Bid Form. <br />Item <br />Bid Description <br />Units <br />Estimated <br />Unit Price <br />Extended <br />No. <br />Quantity <br />Total <br />37 <br />Sewer Valve Boxes for <br />EA <br />4 <br />$125.00 <br />$500.00 <br />Tracer Wire <br />38 <br />Rip -Rap for Outfall L <br />LS <br />1 <br />$29500.00 <br />$2,500 <br />Ditch Crossing <br />39 <br />Re- staking of Ebi <br />LS <br />1 <br />$500.00 <br />$500.00 <br />Property <br />