Orange County NC Website
<br />project to cover the total cost estimate of approximately $643,290 for the project. The <br />remaining $118,490 would come from insurance proceeds. This budget amendment <br />provides for the transfer of $174,800, and amends the following Capital Project <br />Ordinances: <br /> <br />Roofing and Building Façade Project (-$174,800) - Project # 30002 <br /> <br />Revenues for this project: <br /> Current <br />FY 2018-19 <br />FY 2018-19 <br />Amendment <br />FY 2018-19 <br />Revised <br />Alternative Financing $1,267,954 ($174,800) $1,093,154 <br />From County Capital $100,000 $0 $100,000 <br />From General Fund $1,171,000 $0 $1,171,000 <br />Total Project Funding $2,639,054 ($174,800) $2,464,254 <br /> <br /> Appropriated for this project: <br /> Current <br />FY 2018-19 <br />FY 2018-19 <br />Amendment <br />FY 2018-19 <br />Revised <br />Roofing and Building Façade <br />Project $2,639,054 ($174,800) $2,464,254 <br />Total Costs $2,639,054 ($174,800) $2,464,254 <br /> <br />Government Services Annex Project ($293,290) - Project # 10008 <br /> <br />Revenues for this project: <br /> Current <br />FY 2018-19 <br />FY 2018-19 <br />Amendment <br />FY 2018-19 <br />Revised <br />Alternative Financing $350,000 $174,800 $524,800 <br />Insurance Proceeds $0 $118,490 $118,490 <br />Total Project Funding $350,000 $293,290 $643,290 <br /> <br /> Appropriated for this project: <br /> Current <br />FY 2018-19 <br />FY 2018-19 <br />Amendment <br />FY 2018-19 <br />Revised <br />Government Services Annex <br />Project $350,000 $293,290 $643,290 <br />Total Costs $350,000 $293,290 $643,290 <br /> <br /> <br />10. While working on the initial site assessment at the Fairview Park, budgeted at $50,000 in <br />FY 2017-18, to determine the scope of future landfill mitigation on the site, the <br />Department of Environment, Agricultural, and Parks and Recreation (DEAPR) discovered <br />that additional assessment work is needed. There were no additional funds budgeted in <br />FY 2018-19 for continued assessment work, but the N.C. Division of Environmental <br />Quality has agreed to pay 100% of the costs of the second round of assessment work <br />totaling $478,529 over an 18 month period. Of this total, $411,529 is anticipated to be <br />expensed and reimbursed in FY 2018-19, while the remaining funds of $67,000 will be <br />included as part of the development of FY 2019-24 Capital Investment Plan. This budget <br />amendment provides for the acceptance of these reimbursable funds from the State, and <br />amends the Fairview Park Improvements Capital Project Ordinance as follows: <br /> <br /> <br /> <br /> <br />5