CHANGE ORDER NO.: 3 <br />Page 1 of 2 <br />CHANGE ORDER <br />CHANGE ORDER NO.: 3 DATE: April 11, 2018 <br />Project: Historic Rogers Road Sewer Expansion Project <br />Contractor: Moffat Pipe, Inc. <br />Engineer /Architect: URS Corporation — North Carolina <br />CONTRACTOR is directed to make the following changes in the Contract Documents. <br />Description: Moffat Pipe, Inc. is requesting the following revisions to the substantial completion and final <br />completion dates of the contract to account for delays in the project considered to be no fault of their own <br />and beyond their control. Specifically they have been delayed with multiple resident concerns, <br />unanticipated site conditions, and excessive weather delays. An itemized list of the number of days <br />associated with specific issues can be found in Attachment A — HRRA Coordination Issues /Delays. <br />These are delays experienced up to March 22, 2018 and does not account for potential future delays from <br />rock blasting, or any other item. <br />Moffat Pipe, Inc. is also requesting an additional $1,385.48 to remove a dead tree that is leaning over the <br />shed located on 7704 Rogers Road property. An additional day for this work has already been included in <br />the itemized list of delays listed seen in Attaclunent A. Moffat Pipe, Inc. is also requesting an additional 2 <br />days and $4,737.03 to clear the trees along Rogers Road that have grown over the existing AT &T lines. <br />The Contractors Change Order Request for this work can be found as Attachment B. <br />CHANGE IN CONTRACT SUM OR PRICE: <br />CHANGE IN CONTRACT TIME OR TIMES: <br />Original Contract Price <br />Original Contract Times <br />$4,782,436.00 <br />Final Completion: July 15, 2018 <br />Net change from previous Change Orders No. 1 to <br />Net change from previous Change Orders No. l to <br />No.2 : - $110,233.03 <br />No. 2 : 0 days <br />Contract Sum or Price prior to this Change Order <br />Contract Times prior to this Change Order <br />$45672,202.97 <br />Final Completion: July 15, 2018 <br />Net Increase of this Change Order <br />Net Increase of this Change Order <br />$6,122.51 <br />Eight six (86) calendar days <br />Contract Sum or Price with all approved Change <br />Contract Times with all approved Change Orders <br />Orders <br />$4,6781325.48 <br />Final Completion: October 9, 2018 <br />