TIP/WBS # Description Start/Let date Completion Date Status Cost Comments
<br />R-5787B
<br />44917.3.3
<br />Curb ramp improvements at various intersections in Orange and
<br />Alamance Co.
<br />Dec. 2016 Apr. 2017 Planning and design
<br />activities underway.
<br />$100,000 TAP, DMP
<br />SS-4907BF
<br />44271.1.FD1
<br />44271.2.1
<br />44271.3.1
<br />Radius and sight distance improvements at the intersection of SR
<br />1567 (Pleasant Green Road) and SR 1569 (Cole Mill Road) in
<br />Orange Co.
<br />4/18/2016 10/28/2016 Clearing and grading
<br />underway, Frontier utility
<br />relocation completed
<br />$15,000 PE
<br />$80,000 R/W
<br />$53,600 CON
<br />State Spot Safety, R/W plans
<br />received 7/8/15, Constr. By State
<br />Forces
<br />SS-4907BS
<br />44894.2.1
<br />44894.3.1
<br />Installation of traffic signal at the intersection of US70 and SR 1114
<br />(Buckhorn Road) East of Mebane.
<br />Apr. 2017 Jun. 2017 Signal design underway. $40,500 R/W
<br />$43,200 CON
<br />State Spot Safety, Constr. By
<br />State Forces, May need R/W
<br />U-3306(L)
<br />34913.3.2
<br />Landscaping on SR 1733 (Weaver Dairy Road) from NC 86 to SR
<br />1734 (Erwin Road).
<br />Dec. 2016 Spring 2017 Contract let pending $58,645 Project funding, Division let
<br />U-5549/SS-4907AZ
<br />50153.3.F1
<br />44227
<br />44247
<br />Churton Street Access Improvements - Traffic signal and curb ramp
<br />revisions on east side of NC 86 (Churton Street) at SR 1150/SR
<br />1002 (King Street), and NC 86 (Churton Street) at Margaret Street.
<br />Grading, curb & gutter, crosswalks and signal modifications on the
<br />west side of NC 86 /US 70 Bus.(Churton Street) from Tryon Street
<br />to just south of Margaret Street. Grading, curb & gutter, crosswalk
<br />and bus pull-out on NC 86 / US 70 Bus. (Churton Street) from south
<br />of Margaret Street to just south of Nash and Koolock Street in
<br />Hillsborough.
<br />11/14/2016 Spring 2017 FHWA Construction
<br />Authorization approved, No
<br />bids received on Mar 17 let
<br />and April 13 re-let. 3rd let
<br />scheduled with floating
<br />availability date
<br />$156,000 CON
<br />$245,000 CON
<br />$120,000 CON
<br />Spot Safety-State (ADA curb
<br />ramp). Combine with Small
<br />Construction, Contingency, STP-
<br />DA. PCE approved Feb. 2015.
<br />LAP - Town of Hillsborough, MA
<br />executed
<br />U-5550
<br />50154.3.FS1
<br />Intersection improvements at Fordham Boulevard (US15/501) and
<br />Ephesus Church Rd. Improvements will include bike lanes and
<br />sidewalks.
<br />1/27/2016 Mar. 2017 Under construction - 40%
<br />complete
<br />$2,170,000 National Highway Performance
<br />Program, LAP - Town of Chapel
<br />Hill, MA executed
<br />U-5846
<br />50236.1.1
<br />50236.2.1
<br />50236.3.1
<br />Construct a Roundabout at SR 1772 (Greensboro Street) and SR
<br />1780 (Estes Drive) in Carrboro.
<br />Jan. 2018 Mar. 2019 Planning and design
<br />activities underway, R/W
<br />plans complete Jan. 2017
<br />$775,000 STIP, P3.0, PEF-SEPI, Surveys
<br />received 3/15, DMP, Public
<br />meeting on Nov. 14
<br />U-5847
<br />50238.1.1
<br />50238.2.1
<br />50238.3.1
<br />Intersection improvements at SR 1010 (West Franklin St.) and SR
<br />1771 (Merritt Mill Rd)/SR1927 (Brewer Lane) in Chapel Hill /
<br />Carrboro.
<br />Jan. 2019 Mar. 2019 Planning and design
<br />activities underway, R/W
<br />plans complete Jan. 2018
<br />$775,000 STIP, P3.0, PEF-STANTEC,
<br />Surveys received, traffic forecast
<br />and analysis complete, DMP
<br />U-5854
<br />46382.1.1
<br />46328.2.1
<br />46382.3.1
<br />Construct a roundabout at SR 1008 (Mt. Carmel Church Road) and
<br />SR 1913 (Bennett Road) in Chapel Hill
<br />Jul. 2017 Oct. 2018 Planning and design
<br />activities underway, R/W
<br />plans complete October
<br />2016, Public comments
<br />have been received
<br />$775,000 STIP, P3.0,PEF-SEPI, DMP
<br />W-5707A
<br />44853.1.1
<br />Curb ramp improvements for ADA compliance at the following
<br />intersections: SR 2048 (South Road) at Raleigh Street; SR 2048
<br />(South Road) at Country Club Road, SR 1902 (Manning Drive) at
<br />Paul Hardin Drive, and SR 1902 (Manning Drive) at Ridge Road /
<br />Skipper Bowles Road in Chapel Hill
<br />3/16/2017 5/1/17 Planning and design
<br />activities underway.
<br />$10,000 PE HSIP, DMP
<br />NCDOT DIV 7 PROJECTS LOCATED IN DCHCMPO
<br />Item 6.a.
<br /> 73
|