DocuSign Envelope ID: B49FB256 -4ADF- 4759- AF63- 134AD44FC239 <br />weather station acceptable to the Owner and that such alleged greater than <br />reasonably anticipated inclement weather actually delayed the Work or portions <br />thereof which had an effect upon the Contract Time, the Contractor shall not be <br />entitled to an extension of time. <br />For the purpose of this contract, the Contractor agrees to anticipate and plan for <br />inclement weather for the number of calendar days in accordance with the following <br />table: <br />Planned Days/Month <br />Jan <br />7 <br />May <br />7 <br />Sep <br />5 <br />Feb <br />6 <br />Jun <br />6 <br />Oct <br />5 <br />Mar <br />7 <br />Jul <br />8 <br />Nov <br />5 <br />Apr <br />6 <br />Aug <br />6 <br />Dec <br />6 <br />Also the Contractor agrees that the calculation of the number of excessive inclement <br />weather days shall be the number of days in excess of those shown for each month <br />in the table above, in which precipitation exceeded .10 inch, or in which the highest <br />temperature was 32 degrees F. or less as recorded at the approved weather station. <br />If the total accumulated number of calendar days lost to excessive inclement <br />weather, from the notice -to- proceed until the building is enclosed, exceeds the total <br />accumulated number to be reasonably anticipated for the same period from the table <br />above, time for completion will be extended by the number of calendar days needed <br />to include the excess number of calendar days lost. No change in Contract Sum will <br />be authorized because of adjustment of Contract Time due to excessive inclement <br />weather. <br />B. Insert a new Paragraph 8.4 as follows: <br />8.4 "DELAYS AND OVERTIME" <br />8.4.1 The Owner, if it deems necessary, may direct the Contractor to work <br />overtime and if so directed the Contractor shall work said overtime and, provided <br />that the progress of the Work or of the Project has not been delayed by any fault <br />or neglect or act or failure to act of the Contractor or any of its Subcontractors, <br />officers, agents, servants or employees, the Owner will pay the Contractor for <br />such actual additional wages paid, if any, at rates which have been approved by <br />the Owner, plus taxes imposed by law on such additional wages, plus worker's <br />compensation insurance, liability insurance and levies on such wages as required <br />to be paid by the Contractor. <br />8.4.2 If the progress of the Work or of the Project is delayed by any fault or <br />neglect or act or failure to act of the Contractor or any of its Subcontractors, <br />officers, agents, servants or employees, then the Contractor shall, in addition to <br />all of the other obligations in such case, at its own cost and expense, work such <br />overtime as may be necessary to make up for all time lost and to avoid delay in <br />the completion of the Work and of the Project. <br />SGC - 11 <br />