KET <br />(iv) once the infrastructure is removed from the property, owner shall obtain the necessary <br />Erosion Control permits to re- stabilize the property. The time frame for completion shall be <br />determined by the Orange County Erosion Control Officer. Agreed. <br />(v) Upon removal of the facility, the Department shall cause a notice to be recorded within <br />the Orange County Registrar of Deeds office indicating the Class A Special Use Permit has been <br />revoked. Agreed <br />Ili. Anticipated Development Schedule for Completion of the Project <br />Construction is expected to begin within 4 months of receipt of the Interconnection Agreement and <br />associated Power Purchase Agreement from Duke Energy. Construction is expected to take around 4 <br />months. The site is expected to be operational by the end of 2018. <br />