59 <br /> Orange County Transit Plan April 25, 2017 <br /> The original Plan included a project referred to as "Martin The capital funding plan is also different from the original Plan. <br /> Luther King Jr. Boulevard Bus Lanes and Corridor The original Plan assumed a federal funding share of 50 percent <br /> Improvements," with the project boundary starting at Eubanks and a state share of 25 percent. Chapel Hill Transit expects to <br /> Road near 1-40 and ending at the University of North Carolina apply for a grant from the FTA Section 5309 Small Starts <br /> (UNC) campus. The project was not well defined at that time. program for 70 percent of the project cost. The amount of <br /> funds committed from the dedicated Tax District revenue is <br /> During the North-South Corridor Study, which was guided by currently $6.1 million YOE, to be accessed on a pay-as-you-go <br /> significant public and stakeholder involvement, the project basis, which is the same amount dedicated in the original Plan. <br /> scope was extended beyond UNC to the Southern Village Park This amount can be considered a minimum and will be revisited <br /> and Ride lot. The study began in 2014 and concluded in the in the future if local transit revenues are available. The <br /> 2016 with the adoption of the LPA. In November 2016, the anticipated capital funding plan for the project is presented in <br /> North-South BRT Project was accepted into the FTA's Small Table 4.5-1. <br /> Starts Project Development phase where it will be further <br /> defined and shaped. As the project proceeds through the Project Development <br /> phase, Chapel Hill Transit will refine the cost estimates, <br /> continue to apply for State funding and explore other funding <br /> The estimated capital cost of the project is $125.8 million YOE, opportunities. <br /> an increase in cost from the original Plan. The project is Table 4.5-1: N-S BRT Project Capital Funding Plan(YOE millions) <br /> currently scheduled to open in calendar year 2022, although <br /> the opening date is subject to change based on the outcome of - - ° <br /> the project's environmental and design work. Tax-District Revenue $6.1 $6.1 <br /> Federal Funds $12.3 $88.1 <br /> State Funds $6.1 $0.0 <br /> Buses operate every <br /> 4 minutes and have Other Funds $0.0 $31.6 standing room only <br /> Exceeding Total $24.5 $125.8 <br /> Mft seated °fa <br /> All <br /> - = capacity by <br /> As in the original Plan, there are no funds from the dedicated <br /> Tax District Revenues that are planned for the operating cost of <br /> the N-S BRT Project. <br /> Final Page 35 of 65 <br />