z <br />Bidders were asked to submit a price per day that would be paid as a premium for bringing the <br />project on line earlier in an attempt to meet the August 25, 2006 opening day of school. The <br />$4,000 per day cost, however, is not recommended as part of this bid award, <br />Bids for the remaining portion of the project that will provide sewer services to the North <br />Buckhorn/Central Efland area will be solicited fallowing the successful negotiation for right-of- <br />way with the Norfolk Southern Railroad and the subsequent approval by the State and Federal <br />grant funding and regulatory agencies, <br />FINANCIAL IMPACT: Attachment 3 of this abstract, Projected Cost of Utility Extension, <br />outlines the projected costs of extending water and sanitary sewer services to the Buckhorn <br />Area, including the new Gravelly Hill Middle School. As indicated in the table, the project needs <br />$1,4 million in additional funding in order to complete construction of the system. It is important <br />to note that this amount covers the projected costs far the water and sanitary sewer services to <br />the Buckhorn Area, including the new Gravelly Middle School and does not include cost <br />estimations associated with the North BtackhornlCentral Efland area. <br />In February 2006, the Budget Director reviewed County capital projects with available (unspent) <br />pay-as-you-go funds to ascertain if the Baard might be able to defer funding from certain <br />currently funded projects and reallocate them to the water and sewer project. Her review was <br />centered on two areas: (1) availability of unspent funds, and (2) criticality and timeline of current <br />County projects. At its March 15, 2006 budget and capital work session, the Board offered <br />further direction on funding possibilities for the water and sewer project. The intention would be <br />that the Board would reinstate any deferrals from currently funded County projects in future <br />years' Capital Investment Plans. After the March meeting and further discussions with other <br />departments, staff proposes the following pay-as-you-go projects be deferred to complete the <br />water and sewer project: <br />Recommended Deferrals of Currently Funded Pay-As-You- <br />Go Capital Proiects <br />Carrboro Library <br />50,000 <br />____ ~~$~_~~~~ <br />_ <br />~ Replacements <br />Floorin <br />$100,000 <br />HVAC Re airs/Re Iacements $115,000 <br />Painting Exterior and Interior Surfaces $100,000 <br />Roofin Re airs/Re Iacements $100,000 <br />Water roofing $150,000 <br />Total Deferred Projects $615,000 <br />In addition, as suggested by the BQCC, staff recommends that the Board transfer $391,000 <br />from the County's General Fund to the Efland Sewer Capital Project, This amount is equal to <br />the amount of monies that the Baard approved for transfer from the School/Park Reserve to the <br />General Fund in June 2005, <br />The total of all recommended transfers equals $1,006,000, which is $394,000 short of the total <br />funding needed to complete the Buckhorn Area/Gravelly Middle School water and sewer <br />system. In order to fund the project completely, staff further recommends that the Board <br />approve a plan to debt finance the remaining $394,000 with the next debt issuance planned for <br />fall 2006.. Staff anticipates that the additional financing will not cause the County to exceed the <br />