46� <br /> Webb Proposal p. 2 <br /> PHASE 2 cant. <br /> Adjust program to incorporate review information and proposed budget <br /> Prepare detailed Drawings of proposed improvements <br /> Prepare revised cost estimates <br /> Estimated Time for Phase 2. 30 days <br /> Fee Allocation for Phase 2. 207. of total <br /> PHASE 3. CONSTRUCTION DOCUMENTS <br /> SCOPE: <br /> Prepare final Drawings and Specifications <br /> Secure final approval from regulatory agencies <br /> Revise cost estimates as required <br /> Estimated Time for Phase 3. 20 days <br /> Fee Allocation for Phase 3. 307. of total <br /> PHASE 4. BIDDING AND CONTRACTS <br /> SCOPE: <br /> Advertise for Bids <br /> Receive Bids <br /> Prepare Contract Documents <br /> Estimated Time for Phase 4. 30 days <br /> Fee Allocation for Phase 4. 57. of total <br /> PHASE 5. PROJECT CONSTRUCTION <br /> SCOPE: <br /> Supervise Construction <br /> Review Shop Drawings and other Documents <br /> Certify request for payment <br />